| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.95
| 0.85 | 0.10 | $66,650.00 | $6,665.00 |
| 12 | UNCLASSIFIED FILL (CHANNEL) | 7,472.00 | CY |
5,500.00
| 5,272.00 | 228.00 | $32.00 | $7,296.00 |
| 14 | STRUCTURE BACKFILL | 29.00 | CY |
29.00
| 0.00 | 29.00 | $340.00 | $9,860.00 |
| 16 | PCC PAVEMENT | 164.00 | CY |
164.00
| 0.00 | 164.00 | $954.00 | $156,456.00 |
| 22 | CABLE RAILING (CALTRANS STD PLAN B11-47) | 127.00 | LF |
127.00
| 0.00 | 127.00 | $259.00 | $32,893.00 |
| 33 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.65 | 0.15 | $12,420.00 | $1,863.00 |