Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 2/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
25SUBMERSIBLE PUMPS1.00LS 0.44 0.000.44$108,080.00$47,555.20
S-11NON-WORKING DAYS FOR PUMP 3 COMPLETION NWD 55.00 0.0055.00$0.00$0.00
S-12DRILLED HOLES FOR LIGHTING CONDUIT ROUTING LS 1.00 0.001.00$1,500.00$1,500.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,856,555.90 $3,807,500.70 $49,055.20
Retained $192,827.80 $190,375.04 $2,452.76
Deducted $0.00 $0.00 $0.00
Due $3,663,728.10 $3,617,125.66 $46,602.44



Contact Office Engineer
Contractor Copy  