| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
2.00
| 0.00 | 2.00 | $1,500.00 | $3,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $4,000.00 | $1,000.00 |
| 6 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $57,807.00 | $14,451.75 |
| 7 | PROPOSED LAYOUT OVERLAYED ON SITE SURVEY | 40.00 | EA |
19.00
| 0.00 | 19.00 | $392.00 | $7,448.00 |
| 8 | CONCRETE REMOVAL WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
28.39
| 0.00 | 28.39 | $1,661.00 | $47,155.79 |
| 9 | CONCRETE REMOVAL OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
30.50
| 0.00 | 30.50 | $600.00 | $18,300.00 |
| 10 | CONCRETE REPLACEMENT WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
35.46
| 0.00 | 35.46 | $1,837.00 | $65,140.02 |
| 11 | CONCRETE REPLACEMENT OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
30.17
| 0.00 | 30.17 | $600.00 | $18,102.00 |
| S-3 | GROUNDING REBAR MAT AT SOLAR PANEL LOCATIONS (CO #3) | | LS |
1.00
| 0.00 | 1.00 | $9,836.19 | $9,836.19 |
| S-4 | MODIFY LOCATION #14 FROM HARDWIRE TO SOLAR (CO #4) | | LS |
1.00
| 0.00 | 1.00 | $6,770.40 | $6,770.40 |