Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Advertising Bus Shelter Replacement Project (Phase 1)
Contractor: LBI
510 E. Jamie Ave
La Habra, CA 90631-6842
Project ID: TRN0000024
Federal Number(s): None
Original Contract: $2,089,536.00
Awarded: 11/21/2024
Period Ending: 1/31/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 2.00 0.002.00$1,500.00$3,000.00
5IMPLEMENTATION OF BMPS1.00LS 0.25 0.000.25$4,000.00$1,000.00
6TRAFFIC CONTROL1.00LS 0.25 0.000.25$57,807.00$14,451.75
7PROPOSED LAYOUT OVERLAYED ON SITE SURVEY40.00EA 19.00 0.0019.00$392.00$7,448.00
8CONCRETE REMOVAL WITHIN BUS SHELTER FOOTPRINT200.00CY 28.39 0.0028.39$1,661.00$47,155.79
9CONCRETE REMOVAL OUTSIDE BUS SHELTER FOOTPRINT89.00CY 30.50 0.0030.50$600.00$18,300.00
10CONCRETE REPLACEMENT WITHIN BUS SHELTER FOOTPRINT200.00CY 35.46 0.0035.46$1,837.00$65,140.02
11CONCRETE REPLACEMENT OUTSIDE BUS SHELTER FOOTPRINT89.00CY 30.17 0.0030.17$600.00$18,102.00
S-3GROUNDING REBAR MAT AT SOLAR PANEL LOCATIONS (CO #3) LS 1.00 0.001.00$9,836.19$9,836.19
S-4MODIFY LOCATION #14 FROM HARDWIRE TO SOLAR (CO #4) LS 1.00 0.001.00$6,770.40$6,770.40

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
NON-COMPLIANCE OF THE LOCAL WORKER PARTICIPATIONLS 1.00 0.001.00$1,511.00 $1,511.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,098,494.15 $904,790.00 $193,704.15
Retained $54,924.71 $45,239.50 $9,685.21
Deducted $1,511.00 $0.00 $1,511.00
Due $1,042,058.44 $859,550.50 $182,507.94