Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Marie Canyon Stormwater Disinfection System Upgrade
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001374
Federal Number(s): None
Original Contract: $1,646,300.00
Awarded: 4/15/2025
Period Ending: 3/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 1.00 0.001.00$500.00$500.00
5PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
7PREPARATION OF THE DEBRIS CONTAINMENT AND COLLECTION PLAN1.00LS 1.00 0.001.00$3,690.00$3,690.00
23PREPARATION OF TEMPORARY BYPASS1.00LS 1.00 0.001.00$5,165.00$5,165.00
S-1NTP1 EXTENSION WD 30.00 0.0030.00$0.00$0.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $16,855.00 $0.00 $16,855.00
Retained $842.75 $0.00 $842.75
Deducted $0.00 $0.00 $0.00
Due $16,012.25 $0.00 $16,012.25



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.