Progress Payment 8
Project Name: Metro Gold Line Eastside Access Phase II Calvary Cemetery Pedestrian Path
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016013
Federal Number(s): None
Original Contract: $8,533,000.00
Awarded: 4/4/2025
Period Ending: 3/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 8.00 7.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.64 0.560.08$25,000.00$2,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.64 0.560.08$45,000.00$3,600.00
12OFFICE FACILITIES12.00MTH 8.00 7.001.00$3,000.00$3,000.00
16CONCRETE REMOVAL (NON-REINFORCED)1,477.00CY 1,257.33 1,247.3310.00$120.00$1,200.00
23AC PAVEMENT(PATCH BACK)619.00TON 470.83 295.18175.65$200.00$35,130.00
32PCC WALK, 4" THICK52,563.00SF 35,012.50 27,984.007,028.50$8.00$56,228.00
33PCC CURB RAMPS54.00CY 22.22 13.308.92$680.00$6,065.60
36DETECTABLE WARNING SURFACE205.00SF 165.00 105.0060.00$45.00$2,700.00
381-1/2" CONDUIT (SCH 80 PVC)498.00LF 498.00 350.00148.00$31.00$4,588.00
402" CONDUIT (SCH 80 PVC)165.00LF 40.00 0.0040.00$60.00$2,400.00
423" CONDUIT (SCH 80 PVC)15,544.00LF 13,882.00 12,062.001,820.00$45.00$81,900.00
44INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT270.00LF 270.00 0.00270.00$33.00$8,910.00
454-CAMERA VIDEO DETECTION SYSTEM (COMPLETE)1.00EA 0.50 0.000.50$59,000.00$29,500.00
65DETAIL 8 (ONE-COAT PAINT)90.00LF 90.00 74.0016.00$0.40$6.40
66DETAIL 22 (THERMOPLASTIC)3,309.00LF 2,834.00 0.002,834.00$2.00$5,668.00
69DETAIL 29 (THERMOPLASTIC)726.00LF 433.00 0.00433.00$4.00$1,732.00
70DETAIL 32 (THERMOPLASTIC)5,824.00LF 59.00 0.0059.00$4.00$236.00
71DETAIL 38 (THERMOPLASTIC)1,011.00LF 460.00 0.00460.00$1.70$782.00
73DETAIL 9 (THERMOPLASTIC)8,086.00LF 1,939.00 0.001,939.00$1.50$2,908.50
75DETAIL 27B (ONE-COAT PAINT)12,283.00LF 8,736.00 7,364.001,372.00$0.35$480.20
76DETAIL 27B (THERMOPLASTIC)1,099.00LF 295.00 0.00295.00$1.50$442.50
77PAVEMENT MARKINGS (ONE-COAT PAINT)214.00SF 72.00 45.0027.00$3.40$91.80
78PAVEMENT MARKINGS (THERMOPLASTIC)1,902.00SF 707.50 0.00707.50$6.50$4,598.75
7912" STRIPING (THERMOPLASTIC)913.00LF 106.00 0.00106.00$4.50$477.00
8024" STRIPING (THERMOPLASTIC)1,762.00LF 306.50 0.00306.50$9.00$2,758.50
814" STRIPING (THERMOPLASTIC)1,755.00LF 300.00 0.00300.00$0.60$180.00
826" STRIPING (THERMOPLASTIC)28.00LF 13.00 0.0013.00$0.90$11.70
83REMOVE DETAIL 21 (PAINT)315.00LF 315.00 0.00315.00$0.60$189.00
84REMOVE DETAIL 28 (PAINT)103.00LF 103.00 0.00103.00$1.20$123.60
85REMOVE DETAIL 31 (PAINT)2,788.00LF 2,784.00 0.002,784.00$1.20$3,340.80
86REMOVE DETAIL 8 (PAINT)90.00LF 90.00 0.0090.00$0.60$54.00
87REMOVE DETAIL 22 (THERMOPLASTIC)3,827.00LF 3,362.00 3,361.001.00$1.00$1.00
95REMOVE DETAIL 27B (PAINT)12,283.00LF 3,676.00 0.003,676.00$0.60$2,205.60
97REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)838.00SF 392.50 211.00181.50$3.00$544.50
98REMOVE 12" STRIPING (THERMOPLASTIC)1,755.00LF 198.00 49.00149.00$3.00$447.00
99REMOVE 4" STRIPING (THERMOPLASTIC)2,028.00LF 1,616.00 734.00882.00$0.90$793.80
102INSTALL ONE-POST (ROADSIDE SIGN)19.00EA 9.00 0.009.00$300.00$2,700.00
103INSTALL SIGN (STRAP AND SADDLE BRACKET)7.00EA 2.00 0.002.00$125.00$250.00
104RELOCATE SIGN66.00EA 20.00 0.0020.00$200.00$4,000.00
105REMOVE SIGN16.00EA 1.00 0.001.00$100.00$100.00
106REMOVE SIGN POST5.00EA 3.00 0.003.00$300.00$900.00
126TREE BUBBLER236.00EA 170.00 82.0088.00$130.00$11,440.00
130LED LUMINAIRES (200W HPS EQUIVALENT)3.00EA 3.00 0.003.00$500.00$1,500.00
133INSTALL STREETLIGHT POLE24.00EA 24.00 0.0024.00$2,300.00$55,200.00
142COMPOSITE TYPE 2 PULL BOX4.00EA 2.00 0.002.00$1,000.00$2,000.00
154PULL BOX TYPE 2 WITH COVER125.00EA 73.00 36.0037.00$750.00$27,750.00
155PULL BOX TYPE 3 WITH COVER13.00EA 11.00 6.005.00$1,300.00$6,500.00
156NO. 8 CONDUCTORS77,600.00LF 1,882.00 345.001,537.00$2.20$3,381.40
157NO. 10 CONDUCTORS980.00LF 980.00 644.00336.00$1.65$554.40
159INSTALL PEDESTRIAN LIGHT POLE74.00EA 46.00 23.0023.00$1,900.00$43,700.00
162TREE WITH TREE WELL PER MOD STD PLAN 519118.00EA 85.00 41.0044.00$720.00$31,680.00
164TYPE 2070 CONTROLLER WITH D4 SOFTWARE1.00EA 0.50 0.000.50$17,254.00$8,627.00
S-4SERVICE PEDESTALS AND PCC FOUNDATIONS LS 1.00 0.001.00$66,900.00$66,900.00
S-6TYPE A RETAINING WALL AT EASTERN AVE LS 1.00 0.001.00$38,000.00$38,000.00
S-8RECONSTRUCT BOX CULVERT AT CB NO. 3 LS 1.00 0.001.00$11,245.00$11,245.00
S-9COMMUNICATION WIRE 19 AWG LS 1.00 0.001.00$14,085.00$14,085.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,462,708.79 $4,866,401.74 $596,307.05
Retained* $273,135.44 $243,320.09 $29,815.35
Deducted $0.00 $0.00 $0.00
Due $5,189,573.35 $4,623,081.65 $566,491.70