Los Angeles County Public Works
Project Management Division III
Progress Payment 10
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 3/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-11NON-WORKING DAYS FOR PUMP 3 COMPLETION NWD 74.00 55.0019.00$0.00$0.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,856,555.90 $3,856,555.90 $0.00
Retained $192,827.80 $192,827.80 $0.00
Deducted $0.00 $0.00 $0.00
Due $3,663,728.10 $3,663,728.10 $0.00



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.