| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.14
| 0.00 | 0.14 | $1,500.00 | $210.00 |
| 5 | EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $10,000) | 10,000.00 | AL |
10,000.00
| 0.00 | 10,000.00 | $1.00 | $10,000.00 |
| 6 | MOBILIZATION | 1.00 | LS |
0.95
| 0.00 | 0.95 | $68,000.00 | $64,600.00 |
| 7 | TRAFFIC CONTROL | 1.00 | LS |
0.14
| 0.00 | 0.14 | $19,000.00 | $2,660.00 |
| 8 | FLASHING ARROW SIGN | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,000.00 | $2,000.00 |
| 10 | 2" CONDUIT (SCH 80 PVC) | 530.00 | LF |
530.00
| 0.00 | 530.00 | $92.00 | $48,760.00 |
| 11 | 3" CONDUIT (SCH 80 PVC) | 280.00 | LF |
280.00
| 0.00 | 280.00 | $160.00 | $44,800.00 |
| 17 | NO. 5 PULL BOX INCL PCC COVER | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,140.00 | $2,280.00 |
| 18 | NO. 6 PULL BOX INCL PCC COVER | 11.00 | EA |
8.00
| 0.00 | 8.00 | $1,352.00 | $10,816.00 |
| 25 | REMOVE MARBELITE TYPE 3 STD (COMPLETE) (EXCL. FOUND.) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,000.00 | $2,000.00 |
| 47 | TEMPORARY TYPE 332 CABINET | 1.00 | EA |
1.00
| 0.00 | 1.00 | $3,500.00 | $3,500.00 |
| 55 | TEMPORARY TYPE 1 STANDARD | 3.00 | EA |
3.00
| 0.00 | 3.00 | $1,500.00 | $4,500.00 |
| 58 | FURNISH AND INSTALL TEMPORARY TYPE 17 STANDARD | 2.00 | EA |
2.00
| 0.00 | 2.00 | $3,000.00 | $6,000.00 |
| S-5 | COST FOR STAMPED TCP FOR CITY PERMIT - CO #5 | | LS |
1.00
| 0.00 | 1.00 | $4,949.51 | $4,949.51 |
| S-6 | RESTORE EXISTING STREET LIGHTING AT WALNUT AVE (CO #6) | | LS |
1.00
| 0.00 | 1.00 | $8,164.86 | $8,164.86 |