Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Florence Neighborhood Mobility (AHSC)
Contractor: Toro Enterprises, Inc.
P.O. Box 6285
Oxnard, CA 93031
Project ID: RDC0016428
Federal Number(s): None
Original Contract: $4,441,362.76
Awarded: 11/7/2025
Period Ending: 3/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.125 0.000.125$35,000.00$4,375.00
5PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.125 0.000.125$90,000.00$11,250.00
7OFFICE FACILITIES12.00MTH 1.00 0.001.00$6,900.00$6,900.00
8MOBILIZATION1.00LS 0.50 0.000.50$380,000.00$190,000.00
9CLEARING AND GRUBBING1.00LS 0.15 0.000.15$21,000.00$3,150.00
10ROOT PRUNE TREE (INCL ROOT CONTROL BARRIER)2.00EA 2.00 0.002.00$1,150.00$2,300.00
12TREE REMOVAL (6"-12" DIAMETER)5.00EA 5.00 0.005.00$935.00$4,675.00
13TREE REMOVAL (13"-24" DIAMETER)5.00EA 5.00 0.005.00$2,750.00$13,750.00
14TREE REMOVAL (25"+ DIAMETER)9.00EA 5.00 0.005.00$3,685.00$18,425.00
15CROWN REDUCTION, TREE (13" - 24" DIAMETER)2.00EA 2.00 0.002.00$1,150.00$2,300.00
16CONCRETE REMOVAL (NON-REINFORCED)304.00CY 75.70 0.0075.70$435.00$32,929.50
17UNCLASSIFIED EXCAVATION3,383.00CY 191.19 0.00191.19$130.00$24,854.70
19CRUSHED MISCELLANEOUS BASE1,971.00CY 164.42 0.00164.42$105.00$17,264.10
32PARTIAL LOCAL DEPRESSION PER STD PLAN 313, CASE B1.00EA 3.00 0.003.00$800.00$2,400.00
36PCC CURB & GUTTER, TYPE A2-VAR2,174.00LF 651.25 0.00651.25$75.00$48,843.75
111TRAFFIC CONTROL1.00LS 0.06 0.000.06$750,000.00$45,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $433,917.05 $0.00 $433,917.05
Retained $21,695.85 $0.00 $21,695.85
Deducted $0.00 $0.00 $0.00
Due $412,221.20 $0.00 $412,221.20



Contact Office Engineer
Contractor Copy  