| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.44
| 0.36 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
7.00
| 6.00 | 1.00 | $4,000.00 | $4,000.00 |
| 10 | MAINTENANCE AND REMOVAL OF TEMPORARY SOUND BARRIER | 1,000.00 | LF |
300.00
| 51.00 | 249.00 | $30.00 | $7,470.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
120.50
| 100.50 | 20.00 | $1,800.00 | $36,000.00 |
| 21 | PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $10,500) | 1.00 | LS |
1.00
| 0.50 | 0.50 | $10,500.00 | $5,250.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.44
| 0.36 | 0.08 | $34,000.00 | $2,720.00 |
| 26 | MOBILIZATION | 1.00 | LS |
0.95
| 0.73 | 0.22 | $2,100,000.00 | $462,000.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
7.00
| 6.00 | 1.00 | $5,000.00 | $5,000.00 |
| 29 | CLEARING AND GRUBBING | 1.00 | LS |
0.75
| 0.50 | 0.25 | $50,000.00 | $12,500.00 |
| 33 | REMOVE EXISTING INTAKE TOWER, CATWALK, AND STAIRWAY | 1.00 | LS |
0.50
| 0.00 | 0.50 | $100,000.00 | $50,000.00 |
| 35 | REMOVE EXISTING STAFF GAGE POSTS | 9.00 | EA |
9.00
| 0.00 | 9.00 | $300.00 | $2,700.00 |
| 40 | DOWNSTREAM RIPRAP (CLASS IV) | 7,571.00 | CY |
3,534.21
| 51.50 | 3,482.71 | $75.00 | $261,203.25 |
| 42 | CRUSHED ROCK | 3,548.00 | CY |
2,105.60
| 0.00 | 2,105.60 | $200.00 | $421,120.00 |
| 67 | 8" CLEANOUT RISER | 4.00 | EA |
3.00
| 2.00 | 1.00 | $6,100.00 | $6,100.00 |
| 68 | 8" DUCK BILL CHECK VALVE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $6,800.00 | $6,800.00 |
| 73 | OGEE WEIR COMPLETE IN PLACE | 1.00 | LS |
0.16
| 0.13 | 0.03 | $410,000.00 | $12,300.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.53
| 0.43 | 0.10 | $6,000,000.00 | $600,000.00 |
|