| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
10.00
| 9.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.50
| 0.45 | 0.05 | $45,000.00 | $2,250.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
10.00
| 9.00 | 1.00 | $15,000.00 | $15,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.45 | 0.05 | $1,700,000.00 | $85,000.00 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
1,562.85
| 1,137.85 | 425.00 | $240.00 | $102,000.00 |
| 28 | CONCRETE REMOVAL (REINFORCED) | 11.00 | CY |
2.67
| 1.50 | 1.17 | $900.00 | $1,053.00 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
12,891.26
| 11,405.26 | 1,486.00 | $100.00 | $148,600.00 |
| 31 | CRUSHED MISCELLANEOUS BASE | 4,311.00 | CY |
2,416.83
| 1,908.83 | 508.00 | $235.00 | $119,380.00 |
| 32 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 301.00 | CY |
107.56
| 89.00 | 18.56 | $525.00 | $9,744.00 |
| 33 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 1,791,804.00 | SF |
822,320.60
| 58,160.00 | 764,160.60 | $0.35 | $267,456.21 |
| 38 | DOUBLE ADJUST MANHOLE | 21.00 | EA |
14.00
| 9.00 | 5.00 | $1,275.00 | $6,375.00 |
| 39 | PMAC PAVEMENT | 16,307.00 | TON |
7,223.37
| 4,641.89 | 2,581.48 | $130.00 | $335,592.40 |
| 72 | 2" CONDUIT (SCH 80 PVC) | 3,735.00 | LF |
2,897.00
| 2,093.00 | 804.00 | $70.00 | $56,280.00 |
| 73 | 3" CONDUIT (SCH 80 PVC) | 4,215.00 | LF |
4,215.00
| 4,109.00 | 106.00 | $100.00 | $10,600.00 |
| 77 | 3-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 9,475.00 | LF |
4,839.00
| 4,484.00 | 355.00 | $5.00 | $1,775.00 |
| 108 | RELOCATE VEHICLE HEAD (COMPLETE) | 18.00 | EA |
10.00
| 8.00 | 2.00 | $675.00 | $1,350.00 |
| 122 | FURNISH AND INSTALL 3" CONDUIT (SCH 40 PVC) | 6,405.00 | LF |
1,984.00
| 127.00 | 1,857.00 | $86.00 | $159,702.00 |
| 206 | IRRIGATION SYSTEM | 1.00 | LS |
0.60
| 0.50 | 0.10 | $1,300,000.00 | $130,000.00 |
| 208 | DECOMPOSED GRANITE, 4" THICK | 5,834.00 | SF |
19.97
| 0.00 | 19.97 | $8.00 | $159.76 |
| 236 | RELOCATE VIDEO DETECTION CAMERA | 10.00 | EA |
4.00
| 0.00 | 4.00 | $2,220.00 | $8,880.00 |
| 247 | COMPOSITE TYPE 3 PULL BOX INCL COVER | 71.00 | EA |
68.00
| 54.00 | 14.00 | $2,650.00 | $37,100.00 |
| 258 | RIVER ROCK COBBLE | 449.00 | TON |
445.00
| 321.00 | 124.00 | $215.00 | $26,660.00 |
| 259 | EDISON 3 INCH NON-METALLIC PVC SCHEDULE 80 WITH PULL TAPE, FITTINGS AND SUPPORTS | 821.00 | LF |
567.00
| 477.00 | 90.00 | $100.00 | $9,000.00 |
| 264 | SAWCUT AND REMOVE EXISTING ASPHALT CONCRETE (AC) | 4,063.00 | LF |
1,130.00
| 834.00 | 296.00 | $10.00 | $2,960.00 |
| 265 | UNCLASSIFIED EXCAVATION (TRENCH) | 591.00 | CY |
184.00
| 139.00 | 45.00 | $185.00 | $8,325.00 |
| 268 | RECONFIGURE VIDEO DETECTION ZONE - 4 CAMERA | 1.00 | EA |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
| 270 | WELD TENON | 15.00 | EA |
9.00
| 3.00 | 6.00 | $3,700.00 | $22,200.00 |
| S-14 | TEMPORARY IRRIGATION CONTROLLERS & SOLENOID SYSTEMS | | T&M |
16,717.87
| 0.00 | 16,717.87 | $1.00 | $16,717.87 |
| S-16 | INSTALL IRRIGATION SLEEVES AND RELOCATE BACKFLOW | | LS |
1.00
| 0.00 | 1.00 | $17,800.00 | $17,800.00 |
| S-18 | PIPELINE RECONSTRUCTION | | LS |
1.00
| 0.00 | 1.00 | $15,100.00 | $15,100.00 |
|