Los Angeles County Public Works
Project Management Division III
Progress Payment 11
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 4/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.98 0.950.03$18,750.00$562.50
5IMPLEMENTATION OF BMPS1.00LS 0.98 0.950.03$93,750.00$2,812.50
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.98 0.950.03$37,500.00$1,125.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.98 0.950.03$14,950.00$448.50
10REMOVAL AND DISPOSAL OF LCP WASTE1.00LS 0.88 0.700.18$28,750.00$5,175.00
14TRAFFIC CONTROL1.00LS 0.98 0.950.03$9,375.00$281.25
20ELECTRICAL1.00LS 0.83 0.750.08$487,566.00$39,005.28
23MISCELLANEOUS MECHANICAL WORKS1.00LS 0.85 0.800.05$15,375.00$768.75
24AXIAL FLOW PUMPS1.00LS 0.9246 0.910.0146$1,908,750.00$27,867.75
25SUBMERSIBLE PUMPS1.00LS 0.75 0.440.31$108,080.00$33,504.80
27VALVES, PIPES AND FITTINGS1.00LS 0.84 0.650.19$67,550.00$12,834.50
31TEMPORARY BYPASS1.00LS 0.60 0.100.50$59,925.00$29,962.50
S-11NON-WORKING DAYS FOR PUMP 3 COMPLETION NWD 102.00 74.0028.00$0.00$0.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,010,904.23 $3,856,555.90 $154,348.33
Retained $200,545.22 $192,827.80 $7,717.42
Deducted $0.00 $0.00 $0.00
Due $3,810,359.01 $3,663,728.10 $146,630.91



Contact Office Engineer