Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Avenue J-12 and 50th Street West Site Improvements Well 4-91
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: WWD4004057
Federal Number(s): XP-99T25001
Original Contract: $4,587,457.00
Awarded: 12/30/2024
Period Ending: 4/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)9.00MTH 5.00 4.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.50 0.400.10$8,000.00$800.00
9TEMPORARY SOUND WALLS1.00LS 1.00 0.750.25$93,500.00$23,375.00
10IMPLEMENTATION OF BMPS1.00LS 0.50 0.400.10$35,000.00$3,500.00
15OFFICE FACILITIES10.00MTH 5.00 4.001.00$3,000.00$3,000.00
20IMPLEMENTATION OF WELL DEVELOPMENT AND TESTING DISCHARGE PLAN1.00LS 1.00 0.500.50$82,500.00$41,250.00
36AQUIFER STEP-DRAWDOWN TEST (SHORT DURATION)1.00EA 1.00 0.001.00$7,920.00$7,920.00
49SPINNER (FLOW METER) SURVEY1.00EA 1.00 0.001.00$9,790.00$9,790.00
50DEVELOPMENT BY PUMPING1.00LS 1.00 0.001.00$50,600.00$50,600.00
51CONSTANT DISCHARGE AQUIFER TEST1.00EA 1.00 0.001.00$27,720.00$27,720.00
52CONTINUOUS RATE AQUIFER PUMP TEST - RECOVERY1.00EA 1.00 0.001.00$4,950.00$4,950.00
55UNCLASSIFIED EXCAVATION (WELL 4-91 PAD)45.00CY 23.00 0.0023.00$255.00$5,865.00
618" WATERMAIN, D.I.1,016.00LF 928.00 855.0073.00$216.00$15,768.00
66TEMPORARY WELL PUMPING AND DISCHARGE EQUIPMENT1.00LS 1.00 0.001.00$98,900.00$98,900.00
73ELECTRICAL WORK1.00LS 0.1347 0.03640.0983$1,049,721.00$103,187.57

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,596,181.57 $2,199,056.00 $397,125.57
Retained* $129,809.08 $109,952.80 $19,856.28
Deducted $0.00 $0.00 $0.00
Due $2,466,372.49 $2,089,103.20 $377,269.29



*This project has an escrow account.

Contact Office Engineer