| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,500.00 | $0.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
7.00
| 7.00 | 0.00 | $500.00 | $0.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 1.00 | 0.00 | $30,000.00 | $0.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $30,000.00 | $0.00 |
| 6 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 1.00 | 0.00 | $100,000.00 | $0.00 |
| 7 | PREPARATION OF SITE SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 9 | PREPARATION OF THE SITE SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $3,000.00 | $0.00 |
| 10 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 11 | REMOVAL AND DISPOSAL OF NON-HAZARDOUS ASBESTOS WASTE | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 12 | PREPARATION OF THE NOISE MITIGATION PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 1.00 | 0.00 | $2,500.00 | $0.00 |
| 13 | CONSTRUCTION OF TEMPORARY SOUND BARRIER | 114.00 | LF |
0.00
| 0.00 | 0.00 | $220.00 | $0.00 |
| 14 | REMOVAL OF TEMPORARY SOUND BARRIER | 1.00 | LS |
0.00
| 0.00 | 0.00 | $20,000.00 | $0.00 |
| 15 | COMMUNITY RELATIONS (ALLOWANCE OF $50,000) | 50,000.00 | AL |
6,500.00
| 6,500.00 | 0.00 | $1.00 | $0.00 |
| 16 | OFFICE FACILITIES | 8.00 | MTH |
8.00
| 8.00 | 0.00 | $25,000.00 | $0.00 |
| 17 | MOBILIZATION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $100,000.00 | $0.00 |
| 18 | ABANDON WATERMAIN | 1.00 | LS |
1.00
| 1.00 | 0.00 | $25,000.00 | $0.00 |
| 19 | 12" WATERMAIN, .25" THICK STL, CML & CMC, WELDED | 2,146.00 | LF |
2,139.00
| 2,139.00 | 0.00 | $650.00 | $0.00 |
| 20 | WATER SERVICE, 1.0", STD PLAN W-5 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $10,000.00 | $0.00 |
| 21 | WATER SERVICE, 1.5", STD PLAN W-5 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $12,000.00 | $0.00 |
| 22 | WATER SERVICE, 1.0", STD PLAN W-7 | 11.00 | EA |
11.00
| 11.00 | 0.00 | $6,000.00 | $0.00 |
| 23 | WATER SERVICE, 2.0", STD PLAN W-7 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 24 | RECONNECT EXISTING WATER SERVICE | 6.00 | EA |
7.00
| 7.00 | 0.00 | $7,000.00 | $0.00 |
| 25 | RECONNECT EXISTING WATER SERVICE WITH NEW METER BOX AND LID | 17.00 | EA |
17.00
| 17.00 | 0.00 | $8,000.00 | $0.00 |
| 26 | AIR RELEASE AND VACUUM VALVE ASSEMBLY, 2" | 2.00 | EA |
2.00
| 2.00 | 0.00 | $10,000.00 | $0.00 |
| 27 | BUTTERFLY VALVE, 250 PSI WWP, 8" | 1.00 | EA |
1.00
| 1.00 | 0.00 | $6,000.00 | $0.00 |
| 28 | BUTTERFLY VALVE, 250 PSI WWP, 10" | 1.00 | EA |
1.00
| 1.00 | 0.00 | $8,000.00 | $0.00 |
| 29 | BUTTERFLY VALVE, 250 PSI WWP, 12" | 9.00 | EA |
9.00
| 9.00 | 0.00 | $10,000.00 | $0.00 |
| 30 | RUBBER FLAPPER CHECK VALVE, 200 PSI WWP, 12" | 1.00 | EA |
1.00
| 0.00 | 1.00 | $50,000.00 | $50,000.00 |
| 31 | 6' X 4' X 6' PRECAST CONCRETE VAULT | 1.00 | EA |
1.00
| 1.00 | 0.00 | $100,000.00 | $0.00 |
| 32 | FIRE HYDRANT, STD PLAN W-10 | 8.00 | EA |
8.00
| 8.00 | 0.00 | $20,000.00 | $0.00 |
| 33 | PUMP WELL ASSEMBLY, TOP DRAINING,STD PLAN W-53, STYLE A | 3.00 | EA |
3.00
| 2.50 | 0.50 | $25,000.00 | $12,500.00 |
| 34 | REMOVE AND DISPOSE OF EXISTING FIRE HYDRANT ASSEMBLY | 7.00 | EA |
7.00
| 7.00 | 0.00 | $5,000.00 | $0.00 |
| 35 | 20" STEEL CASING | 85.00 | LF |
85.00
| 85.00 | 0.00 | $1,000.00 | $0.00 |
| 36 | TRENCH BACKFILL SLURRY (CLASS 140-S-100) | 26.00 | CY |
86.00
| 86.00 | 0.00 | $500.00 | $0.00 |
| 37 | INTERCONNECTION TO EXISTING WATERMAIN | 3.00 | EA |
3.00
| 3.00 | 0.00 | $30,000.00 | $0.00 |
| 38 | RECONNECT EXISTING SAMPLING STATION | 1.00 | EA |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 39 | CATHODIC PROTECTION ANODE AND TEST STATION, STD PLAN W-39 | 1.00 | EA |
1.00
| 1.00 | 0.00 | $15,000.00 | $0.00 |
| 40 | INITIAL VIDEO INSPECTION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 41 | VIDEO INSPECTION | 1.00 | LS |
1.00
| 1.00 | 0.00 | $5,000.00 | $0.00 |
| 42 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 1.00 | 0.00 | $100,000.00 | $0.00 |
| S-1 | EXTEND WORKING HOURS (7AM-5PM) | | WD |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |
| S-1A | MODIFY WORK HOURS (6:30AM-4:30PM) | | WD |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |
| S-2 | TRENCH BACKFILL SLURRY | | LS |
1.00
| 1.00 | 0.00 | $2,100.00 | $0.00 |
| S-3 | USACE SCHEDULE IMPACT | | WD |
5.00
| 5.00 | 0.00 | $0.00 | $0.00 |
| S-4 | UNFORESEEN SUBSURFACE SLURRY | | T&M |
999.90
| 999.90 | 0.00 | $1.00 | $0.00 |
| S-5 | METER BOX WATER INTRUSION | | T&M |
904.07
| 904.07 | 0.00 | $1.00 | $0.00 |
| S-6 | EXPLORATORY EXCAVATION AT CASTLE ROCK | | EA |
1.00
| 1.00 | 0.00 | $1,400.00 | $0.00 |
| S-7 | WATER INTRUSION STA 22+51 | | T&M |
3,304.45
| 3,304.45 | 0.00 | $1.00 | $0.00 |
| S-9 | DAMAGED UNMARKED SERVICE STA 26+80 | | T&M |
6,680.97
| 6,680.97 | 0.00 | $1.00 | $0.00 |
| S-10 | FIRE HYDRANT LATERAL OVER STORM DRAIN | | LS |
1.00
| 1.00 | 0.00 | $18,421.48 | $0.00 |
| S-11 | UNFORESEEN SLURRY | | T&M |
5,367.65
| 5,367.65 | 0.00 | $1.00 | $0.00 |
| S-12 | BREAKAWAY VALVE STA 13+25 | | LS |
1.00
| 1.00 | 0.00 | $2,381.00 | $0.00 |
| S-13 | FLOODED TRENCH | | T&M |
15,601.59
| 15,601.59 | 0.00 | $1.00 | $0.00 |
| S-14 | WASHED-OUT BASE | | LS |
1.00
| 1.00 | 0.00 | $3,760.00 | $0.00 |
| S-15 | REVISED TIE-IN AT CASTLEROCK RD | | LS |
1.00
| 1.00 | 0.00 | $32,000.00 | $0.00 |
| S-16 | ADDITIONAL PAVING | | TONS |
71.00
| 71.00 | 0.00 | $575.00 | $0.00 |
| S-17 | EXCHANGE OF MATERIAL FOR TIME | | LS |
0.00
| 0.00 | 0.00 | $0.00 | $0.00 |
|