Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Beverly Boulevard TSSP - Pomona Boulevard to Pickering Avenue
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010262
Federal Number(s): None
Original Contract: $3,143,113.70
Awarded: 6/22/2023
Period Ending: 4/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.950.05$2,500.00$125.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)15.00MTH 15.00 13.002.00$500.00$1,000.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.950.05$1,000.00$50.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.950.05$10,000.00$500.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.950.05$5,000.00$250.00
6MOBILIZATION1.00LS 1.00 0.950.05$150,250.00$7,512.50
10CONCRETE REMOVAL (NON-REINFORCED)69.00CY 54.00 49.005.00$264.00$1,320.00
14AC PAVEMENT14.00TON 17.00 14.003.00$1,800.00$5,400.00
17PCC CURB, TYPE A1-824.00LF 30.00 24.006.00$120.00$720.00
18PCC CURB & GUTTER, TYPE A2-642.00LF 52.50 42.0010.50$150.00$1,575.00
19PCC CURB & GUTTER, TYPE A2-VAR243.00LF 303.75 243.0060.75$150.00$9,112.50
21PCC WALK, DRIVES & CURB RAMPS, 4" THICK1,282.00SF 1,385.00 1,282.00103.00$14.40$1,483.20
273-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)8,223.00LF 8,006.00 6,606.001,400.00$3.50$4,900.00
33INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT7,820.00LF 6,208.00 5,500.00708.00$13.00$9,204.00
56GPS UTB UNIT AND ANTENNA21.00EA 21.00 5.0016.00$2,050.00$32,800.00
58PED ISOLATION MODULE12.00EA 14.00 12.002.00$100.00$200.00
60TYPE 332 CABINET6.00EA 7.00 6.001.00$21,300.00$21,300.00
10224" YELLOW CONTINENTAL CROSSWALK (THERMOPLASTIC)635.00LF 793.75 635.00158.75$8.60$1,365.25
114#6 WIRE2,542.00LF 1,685.00 700.00985.00$2.90$2,856.50
115#10 WIRE9,125.00LF 7,690.00 3,520.004,170.00$2.30$9,591.00
116#12 WIRE2,635.00LF 2,349.00 1,539.00810.00$1.90$1,539.00
125BATTERY BACKUP SYSTEM (COMPLETE)1.00EA 1.00 0.001.00$12,000.00$12,000.00
126RELOCATE BBS TO NEW CABINET1.00EA 1.00 0.001.00$3,500.00$3,500.00
133TEMPORARY TYPE 332 CABINET2.00EA 3.00 2.001.00$4,000.00$4,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,330,125.35 $3,197,821.40 $132,303.95
Retained $166,453.31 $159,891.09 $6,562.22
Deducted $0.00 $0.00 $0.00
Due $3,163,672.04 $3,037,930.31 $125,741.73