| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.52
| 0.44 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
8.00
| 7.00 | 1.00 | $4,000.00 | $4,000.00 |
| 12 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.50
| 0.00 | 0.50 | $10,000.00 | $5,000.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
141.50
| 120.50 | 21.00 | $1,800.00 | $37,800.00 |
| 22 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN ($300,000 ALLOWANCE) | 300,000.00 | AL |
50,000.00
| 0.00 | 50,000.00 | $1.00 | $50,000.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.52
| 0.44 | 0.08 | $34,000.00 | $2,720.00 |
| 24 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
0.50
| 0.00 | 0.50 | $14,000.00 | $7,000.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
8.00
| 7.00 | 1.00 | $5,000.00 | $5,000.00 |
| 28 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.50
| 0.15 | 0.35 | $35,000.00 | $12,250.00 |
| 33 | REMOVE EXISTING INTAKE TOWER, CATWALK, AND STAIRWAY | 1.00 | LS |
0.85
| 0.50 | 0.35 | $100,000.00 | $35,000.00 |
| 37 | UNCLASSIFIED EXCAVATION | 8,927.00 | CY |
8,283.00
| 5,141.00 | 3,142.00 | $40.00 | $125,680.00 |
| 39 | BUTTRESS FILL | 16,505.00 | CY |
13,717.10
| 7,621.60 | 6,095.50 | $55.00 | $335,252.50 |
| 42 | CRUSHED ROCK | 3,548.00 | CY |
3,059.60
| 2,105.60 | 954.00 | $200.00 | $190,800.00 |
| 59 | MSE RETAINING WALLS | 1,500.00 | SF |
1,875.00
| 1,500.00 | 375.00 | $200.00 | $75,000.00 |
| 66 | STRUCTURE & ROADWAY FOUNDATION PREPARATION | 2,478.00 | CY |
2,300.00
| 1,726.18 | 573.82 | $60.00 | $34,429.20 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.59
| 0.53 | 0.06 | $6,000,000.00 | $360,000.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.24
| 0.20 | 0.04 | $700,000.00 | $28,000.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.20
| 0.16 | 0.04 | $454,000.00 | $18,160.00 |
| 83 | INSTRUMENTATION | 1.00 | LS |
0.42
| 0.00 | 0.42 | $425,000.00 | $178,500.00 |
| 84 | AUTOMATED DATA ACQUISITION SYSTEM (ADAS) | 1.00 | LS |
0.14
| 0.07 | 0.07 | $72,000.00 | $5,040.00 |
| S-01 | RELOCATE PULL BOXES AND ELECTRICAL DUCT BANK | | LS |
1.00
| 0.00 | 1.00 | $94,000.00 | $94,000.00 |
| S-02 | REMOVE ELECTRICAL DUCT BANK | | T&M |
15,651.92
| 0.00 | 15,651.92 | $1.00 | $15,651.92 |
| S-04 | ADDITIONAL MSE RETAINING WALL | | T&M |
87,500.00
| 0.00 | 87,500.00 | $1.00 | $87,500.00 |
|