Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: South Street TSSP - Atlantic Avenue to Studebaker Road
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TSM0010286
Federal Number(s): None
Original Contract: $687,441.00
Awarded: 7/15/2025
Period Ending: 4/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)7.00MTH 2.00 1.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.28 0.140.14$1,500.00$210.00
7TRAFFIC CONTROL1.00LS 0.28 0.140.14$19,000.00$2,660.00
18NO. 6 PULL BOX INCL PCC COVER11.00EA 9.00 8.001.00$1,352.00$1,352.00
21REMOVE PULL BOX AND RESURFACE SIDEWALK5.00EA 3.00 0.003.00$1,500.00$4,500.00
27REMOVE VEHICLE HEAD (COMPLETE)18.00EA 4.00 0.004.00$200.00$800.00
32REMOVE TYPE 3 FOUNDATION2.00EA 2.00 0.002.00$1,000.00$2,000.00
35REMOVE TYPE 332 CABINET FOUNDATION1.00EA 1.00 0.001.00$815.00$815.00
372070 7G GPS MODULE AND ANTENNA3.00EA 3.00 0.003.00$1,915.00$5,745.00
38TYPE 2070 CONTROLLER4.00EA 2.00 0.002.00$10,825.00$21,650.00
39OMNI EX PROGRAM4.00EA 4.00 0.004.00$2,698.00$10,792.00
40SWITCH PACK11.00EA 11.00 0.0011.00$47.00$517.00
41PED ISOLATION MODULE1.00EA 1.00 0.001.00$103.00$103.00
42REMOVE CONFLICT MONITOR3.00EA 3.00 0.003.00$200.00$600.00
432010 ECL CONFLICT MONITOR4.00EA 4.00 0.004.00$2,250.00$9,000.00
442-CHANNEL ILD SENSOR UNIT17.00EA 17.00 0.0017.00$185.00$3,145.00
48TYPE 332 CABINET FOUNDATION1.00EA 1.00 0.001.00$3,200.00$3,200.00
49TYPE III-BF SERVICE CABINET 1.00EA 1.00 0.001.00$6,318.00$6,318.00
51TYPE 1 STANDARD3.00EA 2.00 0.002.00$2,175.00$4,350.00
52TYPE 15 STANDARD2.00EA 1.00 0.001.00$7,500.00$7,500.00
59TYPE 1 STANDARD FOUNDATION3.00EA 3.00 0.003.00$2,350.00$7,050.00
60TYPE 15 STANDARD FOUNDATION2.00EA 2.00 0.002.00$3,800.00$7,600.00
61TYPE 19 STANDARD FOUNDATION4.00EA 3.00 0.003.00$7,200.00$21,600.00
69PEDESTRIAN PUSH BUTTON POST FOUNDATION1.00EA 1.00 0.001.00$665.00$665.00
715-12" LED VEHICLE HEAD (COMPLETE) 15.00EA 4.00 0.004.00$2,049.00$8,196.00
S-2RFI #2 RESPONSE - CONSTRUCTION NOTE #35 T&M 1,698.35 0.001,698.35$1.00$1,698.35

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $350,806.72 $218,240.37 $132,566.35
Retained $17,540.34 $10,912.02 $6,628.32
Deducted $0.00 $0.00 $0.00
Due $333,266.38 $207,328.35 $125,938.03