Progress Payment 1
Project Name: Marvin Braude Bike Path at Dockweiler Beach Rpr Off-System (JAN 8 2023 WINTER STM)
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0016596
Federal Number(s): None
Original Contract: $1,125,300.00
Awarded: 12/3/2025
Period Ending: 4/30/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)2.00MTH 2.00 0.002.00$500.00$1,000.00
4PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 1.00 0.001.00$50,000.00$50,000.00
6OFFICE FACILITIES2.00MTH 2.00 0.002.00$15,000.00$30,000.00
7MOBILIZATION1.00LS 1.00 0.001.00$110,000.00$110,000.00
8CONCRETE REMOVAL (NON-REINFORCED)335.00CY 335.00 0.00335.00$300.00$100,500.00
9CONCRETE REMOVAL (REINFORCED)60.00CY 27.00 0.0027.00$500.00$13,500.00
10UNCLASSIFIED EXCAVATION902.00CY 902.00 0.00902.00$150.00$135,300.00
11STABILIZATION GEOTEXTILE1,518.00SY 1,518.00 0.001,518.00$5.00$7,590.00
12CRUSHED MISCELLANEOUS BASE236.00CY 236.00 0.00236.00$225.00$53,100.00
13PCC PAVEMENT382.00CY 382.00 0.00382.00$700.00$267,400.00
14CONST & REMOVE TEMP CHAIN LINK FENCE496.00LF 496.00 0.00496.00$50.00$24,800.00
15TEMPORARY RAILING (TYPE K)476.00LF 476.00 0.00476.00$65.00$30,940.00
16REINFORCED POLYETHYLENE GEOMEMBRANE11,264.00SF 11,264.00 0.0011,264.00$3.00$33,792.00
175' X 10' X 1" THICK STEEL PLATE (STAGING AREA)12,978.00SF 12,800.00 0.0012,800.00$7.00$89,600.00
18UNCLASSIFIED EXCAVATION (STAGING AREA)361.00CY 361.00 0.00361.00$100.00$36,100.00
19TRAFFIC CONTROL1.00LS 1.00 0.001.00$117,932.00$117,932.00
S-1PEDESTRIAN PAD LS 1.00 0.001.00$25,000.00$25,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,131,554.00 $0.00 $1,131,554.00
Retained $56,577.70 $0.00 $56,577.70
Deducted $0.00 $0.00 $0.00
Due $1,074,976.30 $0.00 $1,074,976.30