Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Dominguez Pump Station Rehabilitation
Contractor: Innovative Construction Solutions
575 Anton Blvd. Suite 850
Costa Mesa, CA 92626
Project ID: FCC0001393
Federal Number(s): None
Original Contract: $7,669,929.00
Awarded: 4/10/2025
Period Ending: 6/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.20 0.000.20$15,000.00$3,000.00
5IMPLEMENTATION OF BMPS1.00LS 0.20 0.000.20$5,000.00$1,000.00
6PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.20 0.000.20$20,000.00$4,000.00
8REMOVAL AND DISPOSAL OF LBP/LCP1.00LS 0.80 0.000.80$75,000.00$60,000.00
9REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIAL1.00LS 0.80 0.000.80$20,000.00$16,000.00
10PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
11IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.80 0.000.80$1,500.00$1,200.00
12PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
13IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN1.00LS 0.80 0.000.80$1,500.00$1,200.00
14OFFICE FACILITIES6.00MTH 0.80 0.000.80$11,000.00$8,800.00
16DEMOLITION1.00LS 0.05 0.000.05$150,000.00$7,500.00
19MISCELLANEOUS MECHANICAL WORKS1.00LS 0.15 0.000.15$140,000.00$21,000.00
22ELECTRICAL WORK1.00LS 0.05 0.000.05$1,425,000.00$71,250.00
24REMOVAL OF EXISTING STEEL STRUCTURES1.00LS 0.20 0.000.20$50,000.00$10,000.00
30ACCESS HATCH1.00LS 0.50 0.000.50$10,000.00$5,000.00
35TRAFFIC CONTROL1.00LS 0.50 0.000.50$5,000.00$2,500.00
S-2CRANE CERTIFICATION LS 1.00 0.001.00$13,510.00$13,510.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $237,960.00 $0.00 $237,960.00
Retained $11,898.00 $0.00 $11,898.00
Deducted $0.00 $0.00 $0.00
Due $226,062.00 $0.00 $226,062.00