| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $15,000.00 | $3,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 6 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.20
| 0.00 | 0.20 | $20,000.00 | $4,000.00 |
| 8 | REMOVAL AND DISPOSAL OF LBP/LCP | 1.00 | LS |
0.80
| 0.00 | 0.80 | $75,000.00 | $60,000.00 |
| 9 | REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIAL | 1.00 | LS |
0.80
| 0.00 | 0.80 | $20,000.00 | $16,000.00 |
| 10 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.80
| 0.00 | 0.80 | $1,500.00 | $1,200.00 |
| 12 | PREPARATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 13 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
0.80
| 0.00 | 0.80 | $1,500.00 | $1,200.00 |
| 14 | OFFICE FACILITIES | 6.00 | MTH |
0.80
| 0.00 | 0.80 | $11,000.00 | $8,800.00 |
| 16 | DEMOLITION | 1.00 | LS |
0.05
| 0.00 | 0.05 | $150,000.00 | $7,500.00 |
| 19 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
0.15
| 0.00 | 0.15 | $140,000.00 | $21,000.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
0.05
| 0.00 | 0.05 | $1,425,000.00 | $71,250.00 |
| 24 | REMOVAL OF EXISTING STEEL STRUCTURES | 1.00 | LS |
0.20
| 0.00 | 0.20 | $50,000.00 | $10,000.00 |
| 30 | ACCESS HATCH | 1.00 | LS |
0.50
| 0.00 | 0.50 | $10,000.00 | $5,000.00 |
| 35 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
| S-2 | CRANE CERTIFICATION | | LS |
1.00
| 0.00 | 1.00 | $13,510.00 | $13,510.00 |
|