Los Angeles County Public Works
Project Management Division III
Progress Payment 12
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 5/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.99 0.980.01$18,750.00$187.50
5IMPLEMENTATION OF BMPS1.00LS 0.99 0.980.01$93,750.00$937.50
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.99 0.980.01$37,500.00$375.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.99 0.980.01$14,950.00$149.50
10REMOVAL AND DISPOSAL OF LCP WASTE1.00LS 1.00 0.880.12$28,750.00$3,450.00
14TRAFFIC CONTROL1.00LS 0.99 0.980.01$9,375.00$93.75
20ELECTRICAL1.00LS 0.86 0.830.03$487,566.00$14,626.98
22MECHANICAL DEMOLITION1.00LS 0.91 0.650.26$29,875.00$7,767.50
25SUBMERSIBLE PUMPS1.00LS 1.00 0.750.25$108,080.00$27,020.00
27VALVES, PIPES AND FITTINGS1.00LS 0.87 0.840.03$67,550.00$2,026.50
28PIPE WALL ADAPTER PLATES1.00LS 1.00 0.600.40$26,400.00$10,560.00
S-5AXIAL FLOW PUMP ANCHORAGE LS 0.66 0.220.44$38,700.00$17,028.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 116.11 0.00116.11$1.00 $116.11

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,095,126.46 $4,010,904.23 $84,222.23
Retained $204,756.33 $200,545.22 $4,211.11
Deducted $116.11 $0.00 $116.11
Due $3,890,254.02 $3,810,359.01 $79,895.01