Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: Avenue J-12 and 50th Street West Site Improvements Well 4-91
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: WWD4004057
Federal Number(s): XP-99T25001
Original Contract: $4,587,457.00
Awarded: 12/30/2024
Period Ending: 5/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)9.00MTH 6.00 5.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.60 0.500.10$8,000.00$800.00
10IMPLEMENTATION OF BMPS1.00LS 0.60 0.500.10$35,000.00$3,500.00
15OFFICE FACILITIES10.00MTH 6.00 5.001.00$3,000.00$3,000.00
16MOBILIZATION1.00LS 1.00 0.950.05$624,020.00$31,201.00
29AIR VENT TUBE20.00LF 20.00 0.0020.00$55.00$1,100.00
42REMOVE AND REPLACE PORTION OF FENCE 4-27 AND APPURTENANCES1.00LS 1.00 0.500.50$2,250.00$1,125.00
43MASONRY BLOCK WALL804.00LF 777.00 603.00174.00$303.00$52,722.00
47PLUMBNESS ALIGNMENT AND SURVEY1.00EA 1.00 0.001.00$8,250.00$8,250.00
55UNCLASSIFIED EXCAVATION (WELL 4-91 PAD)45.00CY 45.00 23.0022.00$255.00$5,610.00
578" GATE VALVE, FLG'D, 200 PSI WWP, CL 1251.00EA 1.00 0.001.00$6,740.00$6,740.00
608" FLOW METER1.00EA 1.00 0.001.00$11,346.00$11,346.00
618" WATERMAIN, D.I.1,016.00LF 985.00 928.0057.00$216.00$12,312.00
628" CML & C STL PIPE, 0.25" WALL THICKNESS, WELDED12.00LF 12.00 0.0012.00$2,950.00$35,400.00
638" CML STL PIPE, 0.25" WALL THICKNESS (WELL 4-91)25.00LF 19.00 0.0019.00$4,025.00$76,475.00
658" CHECK VALVE, FLG'D CL 1251.00EA 1.00 0.001.00$34,290.00$34,290.00
71STRUCTURE CONCRETE121.00CY 56.00 0.0056.00$1,200.00$67,200.00
72GRAVEL PAVEMENT14,200.00SF 4,800.00 0.004,800.00$2.50$12,000.00
73ELECTRICAL WORK1.00LS 0.3639 0.13470.2292$1,049,721.00$240,596.05

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 8.00 0.008.00$100.00 $800.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $3,200,348.62 $2,596,181.57 $604,167.05
Retained* $160,017.43 $129,809.08 $30,208.35
Deducted $800.00 $0.00 $800.00
Due $3,039,531.19 $2,466,372.49 $573,158.70



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  