| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $22,137.00 | $4,427.40 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $7,379.00 | $1,475.80 |
| 9 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $23,613.00 | $5,903.25 |
| 10 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.05 | 0.35 | $29,517.00 | $10,330.95 |
| 11 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $11,069.00 | $2,213.80 |
| 12 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $1,181.00 | $1,181.00 |
| 15 | ELECTRICAL WORK | 1.00 | LS |
0.144
| 0.0821 | 0.0619 | $472,583.00 | $29,252.89 |
| 18 | REMOVAL AND RECYCLING OF UNIVERSAL WASTE | 1.00 | LS |
0.90
| 0.00 | 0.90 | $6,641.00 | $5,976.90 |
| 20 | STRUCTURAL WALL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $52,227.00 | $52,227.00 |
| 21 | SCREEN FILTERS | 1.00 | LS |
0.90
| 0.00 | 0.90 | $76,448.00 | $68,803.20 |
| 22 | MECHANICAL DEMOLITION | 1.00 | LS |
1.00
| 0.1527 | 0.8473 | $82,499.00 | $69,901.40 |
| 24 | IMPLEMENTATION OF TEMPORARY BYPASS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $27,095.00 | $6,773.75 |
| S-6 | ANCHORAGE MATERIAL SUBSTITUTION | | LS |
1.00
| 0.00 | 1.00 | $228.82 | $228.82 |