Progress Payment 10
Project Name: Metro Gold Line Eastside Access Phase II Calvary Cemetery Pedestrian Path
Contractor: Los Angeles Engineering, Inc.
633 North Barranca Avenue
Covina, CA 91723
Project ID: RDC0016013
Federal Number(s): None
Original Contract: $8,533,000.00
Awarded: 4/4/2025
Period Ending: 5/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 10.00 9.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.80 0.720.08$25,000.00$2,000.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.80 0.720.08$45,000.00$3,600.00
12OFFICE FACILITIES12.00MTH 10.00 9.001.00$3,000.00$3,000.00
18UNCLASSIFIED EXCAVATION3,925.00CY 2,255.33 2,130.33125.00$135.00$16,875.00
19CRUSHED MISCELLANEOUS BASE2,770.00CY 2,255.95 2,116.35139.60$110.00$15,356.00
26CURB DRAIN PER STD PLAN 150, N=1, CASE 1 INLET116.00EA 96.00 0.0096.00$350.00$33,600.00
28PCC CURB & GUTTER, TYPE A2-64,853.00LF 4,164.73 3,222.00942.73$35.00$32,995.55
32PCC WALK, 4" THICK52,563.00SF 43,060.89 40,422.502,638.39$8.00$21,107.12
33PCC CURB RAMPS54.00CY 26.05 22.223.83$680.00$2,604.40
36DETECTABLE WARNING SURFACE205.00SF 180.00 165.0015.00$45.00$675.00
423" CONDUIT (SCH 80 PVC)15,544.00LF 16,144.00 13,882.002,262.00$45.00$101,790.00
107TRAFFIC CONTROL1.00LS 1.00 0.750.25$317,968.85$79,492.21
109IRRIGATION SYSTEM1.00LS 1.00 0.750.25$485,000.00$121,250.00
111DECOMPOSED GRANITE, 3" THICK1,997.00SF 1,841.40 686.341,155.06$15.00$17,325.90
1133" CONDUIT572.00LF 350.00 180.00170.00$265.00$45,050.00
125RUBBER WALKWAY47,489.00SF 37,668.00 28,960.508,707.50$33.00$287,347.50
126TREE BUBBLER236.00EA 220.00 170.0050.00$130.00$6,500.00
156NO. 8 CONDUCTORS77,600.00LF 3,046.00 2,246.00800.00$2.20$1,760.00
162TREE WITH TREE WELL PER MOD STD PLAN 519118.00EA 110.00 85.0025.00$720.00$18,000.00
174SURVEYING SERVICES1.00LS 1.00 0.750.25$75,000.00$18,750.00
S-12IRRIGATION MAINLINE EXTENSION LS 1.00 0.001.00$32,800.00$32,800.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $7,268,150.28 $6,405,771.60 $862,378.68
Retained* $363,407.51 $320,288.58 $43,118.93
Deducted $0.00 $0.00 $0.00
Due $6,904,742.77 $6,085,483.02 $819,259.75



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.