| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 8 | CONCRETE REMOVAL WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
46.76
| 40.08 | 6.68 | $1,661.00 | $11,095.48 |
| 9 | CONCRETE REMOVAL OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
58.41
| 49.20 | 9.21 | $600.00 | $5,526.00 |
| 10 | CONCRETE REPLACEMENT WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
65.46
| 52.96 | 12.50 | $1,837.00 | $22,962.50 |
| 11 | CONCRETE REPLACEMENT OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
59.78
| 48.87 | 10.91 | $600.00 | $6,546.00 |
| S-5 | AC PATCH BACK AT LOCATION NO.29 (CO #5) | | LS |
1.00
| 0.00 | 1.00 | $8,957.96 | $8,957.96 |
| S-6 | PAD FOR BIKE RACK AND TRASH RECEPTACLE AT LOCATION NO. 33 (CO #6) | | LS |
1.00
| 0.00 | 1.00 | $9,931.32 | $9,931.32 |
| S-7 | NEW COMMUNICATION PULL BOX AT LOCATION NO. 14 (CO #7) | | LS |
1.00
| 0.00 | 1.00 | $5,756.96 | $5,756.96 |
| S-8 | RELOCATE EXISTING WATER LINE AT LOCATION NO. 11 (CO #8) | | LS |
1.00
| 0.00 | 1.00 | $9,454.43 | $9,454.43 |
| S-9 | NEW CONDUITS AND CONDUCTORS AT LOCATION NO. 33 (CO #9) | | LS |
1.00
| 0.00 | 1.00 | $5,278.15 | $5,278.15 |
| S-10 | REPAIR CONDUIT BLOCKAGE AT LOC. NO. 17 (CO #10) | | LS |
1.00
| 0.00 | 1.00 | $7,910.72 | $7,910.72 |