| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
3.00
| 0.00 | 3.00 | $500.00 | $1,500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.375
| 0.25 | 0.125 | $35,000.00 | $4,375.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.375
| 0.25 | 0.125 | $90,000.00 | $11,250.00 |
| 7 | OFFICE FACILITIES | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $6,900.00 | $6,900.00 |
| 8 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $380,000.00 | $95,000.00 |
| 9 | CLEARING AND GRUBBING | 1.00 | LS |
0.75
| 0.25 | 0.50 | $21,000.00 | $10,500.00 |
| 16 | CONCRETE REMOVAL (NON-REINFORCED) | 304.00 | CY |
257.00
| 178.52 | 78.48 | $435.00 | $34,138.80 |
| 17 | UNCLASSIFIED EXCAVATION | 3,383.00 | CY |
2,101.21
| 1,300.92 | 800.29 | $130.00 | $104,037.70 |
| 19 | CRUSHED MISCELLANEOUS BASE | 1,971.00 | CY |
876.34
| 365.44 | 510.90 | $105.00 | $53,644.50 |
| 21 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 29.00 | CY |
12.00
| 0.00 | 12.00 | $385.00 | $4,620.00 |
| 22 | AC PAVEMENT | 1,471.00 | TON |
1,115.00
| 700.00 | 415.00 | $180.00 | $74,700.00 |
| 25 | AC PAVEMENT (PATCHBACK) | 889.00 | SF |
440.00
| 0.00 | 440.00 | $10.00 | $4,400.00 |
| 28 | RECONSTRUCT MANHOLE | 12.00 | EA |
6.00
| 4.00 | 2.00 | $7,500.00 | $15,000.00 |
| 29 | ADJUST MANHOLE | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,600.00 | $3,200.00 |
| 30 | PCC PAVEMENT | 111.00 | CY |
46.66
| 0.00 | 46.66 | $460.00 | $21,463.60 |
| 35 | PCC CURB, TYPE A1-VAR | 91.00 | LF |
17.50
| 0.00 | 17.50 | $65.00 | $1,137.50 |
| 36 | PCC CURB & GUTTER, TYPE A2-VAR | 2,174.00 | LF |
964.72
| 651.25 | 313.47 | $75.00 | $23,510.25 |
| 37 | PCC WALK, 4" THICK | 24,108.00 | SF |
12,806.55
| 5,518.38 | 7,288.17 | $11.55 | $84,178.36 |
| 38 | PCC CURB RAMPS | 71.00 | CY |
47.18
| 64.03 | -16.85 | $2,400.00 | ($40,440.00) |
| 39 | DETECTABLE WARNING SURFACE | 824.00 | SF |
431.80
| 128.15 | 303.65 | $32.00 | $9,716.80 |
| 40 | CROSS GUTTER | 56.00 | CY |
34.16
| 0.00 | 34.16 | $785.00 | $26,815.60 |
| 41 | 3" CONDUIT (SCH 80 PVC) | 405.00 | LF |
405.00
| 0.00 | 405.00 | $208.00 | $84,240.00 |
| 46 | NO. 6 PULL BOX INCL PCC COVER | 11.00 | EA |
4.00
| 0.00 | 4.00 | $2,510.00 | $10,040.00 |
| 81 | STREET LIGHT FOUNDATION | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,467.15 | $2,934.30 |
| 95 | PAVEMENT MARKINGS (THERMOPLASTIC) | 961.00 | SF |
268.00
| 0.00 | 268.00 | $9.30 | $2,492.40 |
| 97 | 12" STRIPING (THERMOPLASTIC) | 1,251.00 | LF |
114.50
| 0.00 | 114.50 | $6.10 | $698.45 |
| 107 | RELOCATE SIGN | 50.00 | EA |
11.00
| 5.00 | 6.00 | $160.00 | $960.00 |
| 109 | RELOCATE SIGN POST | 18.00 | EA |
11.00
| 5.00 | 6.00 | $265.00 | $1,590.00 |
| 111 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.12 | 0.58 | $750,000.00 | $435,000.00 |
| 114 | DETAIL 21 (THERMOPLASTIC) | 1,329.00 | LF |
344.00
| 0.00 | 344.00 | $1.90 | $653.60 |
| 115 | DETAIL 27B (THERMOPLASTIC) | 83.00 | LF |
65.50
| 0.00 | 65.50 | $1.35 | $88.43 |
| 117 | DETAIL 31 (THERMOPLASTIC) | 532.00 | LF |
100.00
| 0.00 | 100.00 | $2.40 | $240.00 |
| 119 | DETAIL 39 (THERMOPLASTIC) | 116.00 | LF |
66.00
| 0.00 | 66.00 | $1.35 | $89.10 |
| 120 | DETAIL 39A (THERMOPLASTIC) | 137.00 | LF |
133.00
| 0.00 | 133.00 | $0.85 | $113.05 |
| 121 | 24" STRIPING (THERMOPLASTIC) | 8,520.00 | LF |
1,517.50
| 0.00 | 1,517.50 | $8.90 | $13,505.75 |
| 124 | 4" STRIPING (THERMOPLASTIC) | 153.00 | LF |
153.00
| 0.00 | 153.00 | $1.15 | $175.95 |
|