| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 7.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.53
| 0.28 | 0.25 | $1,500.00 | $375.00 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $68,000.00 | $3,400.00 |
| 7 | TRAFFIC CONTROL | 1.00 | LS |
0.53
| 0.28 | 0.25 | $19,000.00 | $4,750.00 |
| 27 | REMOVE VEHICLE HEAD (COMPLETE) | 18.00 | EA |
17.00
| 4.00 | 13.00 | $200.00 | $2,600.00 |
| 70 | 3-12" LED VEHICLE HEAD (COMPLETE) | 24.00 | EA |
13.00
| 0.00 | 13.00 | $1,617.00 | $21,021.00 |
| 71 | 5-12" LED VEHICLE HEAD (COMPLETE) | 15.00 | EA |
5.00
| 4.00 | 1.00 | $2,049.00 | $2,049.00 |
| 72 | SALVAGE EQUIPMENT | 1.00 | LS |
0.25
| 0.00 | 0.25 | $8,153.00 | $2,038.25 |