| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 24.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.55 | 0.05 | $45,000.00 | $2,250.00 |
| 16 | OFFICE FACILITIES | 25.00 | MTH |
14.00
| 11.00 | 3.00 | $15,000.00 | $45,000.00 |
| 17 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $2,600,000.00 | $130,000.00 |
| 18 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.55 | 0.05 | $1,700,000.00 | $85,000.00 |
| 20 | DECOMPOSED GRANITE MULCH | 22,238.00 | SF |
21,759.96
| 19,056.00 | 2,703.96 | $3.00 | $8,111.88 |
| 27 | CONCRETE REMOVAL (NON-REINFORCED) | 3,340.00 | CY |
1,950.83
| 1,562.85 | 387.98 | $240.00 | $93,115.20 |
| 29 | UNCLASSIFIED EXCAVATION | 23,912.00 | CY |
13,883.10
| 13,643.26 | 239.84 | $100.00 | $23,984.00 |
| 31 | CRUSHED MISCELLANEOUS BASE | 4,311.00 | CY |
3,389.54
| 3,155.83 | 233.71 | $235.00 | $54,921.85 |
| 34 | AC PAVEMENT(PATCH BACK) | 4,524.00 | TON |
1,482.81
| 1,442.68 | 40.13 | $180.00 | $7,223.40 |
| 38 | DOUBLE ADJUST MANHOLE | 21.00 | EA |
18.00
| 17.00 | 1.00 | $1,275.00 | $1,275.00 |
| 47 | PCC CURB, TYPE A1-VAR | 876.00 | LF |
587.00
| 549.00 | 38.00 | $40.00 | $1,520.00 |
| 49 | PCC CURB & GUTTER, TYPE A2-8 | 2,067.00 | LF |
902.60
| 601.50 | 301.10 | $44.00 | $13,248.40 |
| 50 | PCC CURB & GUTTER, TYPE A2-VAR | 256.00 | LF |
28.00
| 0.00 | 28.00 | $50.00 | $1,400.00 |
| 57 | PCC WALK & DRIVEWAYS, 4" THICK | 38,431.00 | SF |
28,758.27
| 20,871.64 | 7,886.63 | $8.50 | $67,036.36 |
| 58 | PCC CURB RAMPS | 150.00 | CY |
97.27
| 75.52 | 21.75 | $1,200.00 | $26,100.00 |
| 59 | PCC DRIVEWAYS, 6" THICK | 4,910.00 | SF |
1,910.50
| 1,695.50 | 215.00 | $13.00 | $2,795.00 |
| 60 | DETECTABLE WARNING SURFACE | 960.00 | SF |
528.00
| 348.00 | 180.00 | $60.00 | $10,800.00 |
| 71 | 1" CONDUIT (SCH 80 PVC) | 189.00 | LF |
80.00
| 0.00 | 80.00 | $60.00 | $4,800.00 |
| 72 | 2" CONDUIT (SCH 80 PVC) | 3,735.00 | LF |
3,420.00
| 3,347.00 | 73.00 | $70.00 | $5,110.00 |
| 83 | REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.) | 6.00 | EA |
3.00
| 1.00 | 2.00 | $670.00 | $1,340.00 |
| 84 | REMOVE TYPE 15 STANDARD (COMPLETE) (EXCL. FOUND.) | 10.00 | EA |
3.00
| 0.00 | 3.00 | $2,000.00 | $6,000.00 |
| 96 | REMOVE TYPE 1 FOUNDATION | 5.00 | EA |
2.00
| 0.00 | 2.00 | $1,010.00 | $2,020.00 |
| 98 | REMOVE TYPE 15 FOUNDATION | 13.00 | EA |
4.00
| 1.00 | 3.00 | $2,550.00 | $7,650.00 |
| 131 | LED LUMINAIRE (250 W HPS EQUIVALENT) | 33.00 | EA |
20.00
| 19.00 | 1.00 | $1,560.00 | $1,560.00 |
| 144 | TYPE 332 CABINET FOUNDATION | 7.00 | EA |
4.00
| 3.00 | 1.00 | $3,225.00 | $3,225.00 |
| 149 | TYPE 1 STANDARD | 3.00 | EA |
3.00
| 1.00 | 2.00 | $2,420.00 | $4,840.00 |
| 154 | TYPE 1 STANDARD FOUNDATION | 3.00 | EA |
3.00
| 2.00 | 1.00 | $1,575.00 | $1,575.00 |
| 166 | 12' LUMINAIRE MAST ARM | 40.00 | EA |
7.00
| 4.00 | 3.00 | $2,000.00 | $6,000.00 |
| 174 | 3-12" LED VEHICLE HEAD (COMPLETE) | 103.00 | EA |
23.00
| 16.00 | 7.00 | $1,900.00 | $13,300.00 |
| 175 | 5-12" LED VEHICLE HEAD (COMPLETE) | 6.00 | EA |
3.00
| 2.00 | 1.00 | $2,500.00 | $2,500.00 |
| 207 | PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.20
| 0.10 | 0.10 | $52,000.00 | $5,200.00 |
| 211 | LED UPLIGHTS FOR MONUMENT SIGN | 12.00 | EA |
8.00
| 4.00 | 4.00 | $5,575.00 | $22,300.00 |
| 219 | TYPE 15TS STANDARD | 22.00 | EA |
4.00
| 1.00 | 3.00 | $7,000.00 | $21,000.00 |
| 222 | TYPE 15TS STANDARD FOUNDATION | 22.00 | EA |
4.00
| 1.00 | 3.00 | $4,010.00 | $12,030.00 |
| 232 | #8 AWG, XHHW CU CONDUCTOR | 9,640.00 | LF |
2,279.00
| 1,979.00 | 300.00 | $2.35 | $705.00 |
| 234 | RIVER ROCK PAVING, 6" THICK | 30,203.00 | SF |
20,010.95
| 15,715.91 | 4,295.04 | $15.25 | $65,499.36 |
| 255 | LED LUMINAIRE (200W HPS EQUIVALENT) | 26.00 | EA |
18.00
| 16.00 | 2.00 | $1,700.00 | $3,400.00 |
| 261 | 2 INCH DIAMETER NON-METALLIC PVC SCHEDULE 80 BRANCH CONDUIT, FITTINGS AND SUPPORTS | 5,124.00 | LF |
3,040.00
| 2,755.00 | 285.00 | $65.00 | $18,525.00 |
| 263 | PULL BOX, 10 INCH BY 17 INCH BY 12 INCH | 35.00 | EA |
1.00
| 0.00 | 1.00 | $475.00 | $475.00 |
| 267 | RIVER ROCK PAVING, 4" THICK | 42,485.00 | SF |
26,641.73
| 21,411.75 | 5,229.98 | $17.00 | $88,909.66 |
| 274 | LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE) | 31.00 | EA |
8.00
| 3.00 | 5.00 | $1,400.00 | $7,000.00 |
| S-11 | REMOVE AND REPLACE MEDIAN NOSES | | T&M |
25,298.88
| 20,000.00 | 5,298.88 | $1.00 | $5,298.88 |
| S-15 | FURNISH AND INSTALL WEED BARRIER | | T&M |
36,221.72
| 34,788.62 | 1,433.10 | $1.00 | $1,433.10 |
| S-17 | FRONTAGE MEDIAN IMPROVEMENTS | | LS |
1.00
| 0.00 | 1.00 | $201,400.00 | $201,400.00 |
|