Los Angeles County Public Works
Project Management Division III
Progress Payment 13
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 6/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.995 0.990.005$18,750.00$93.75
5IMPLEMENTATION OF BMPS1.00LS 0.995 0.990.005$93,750.00$468.75
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.995 0.990.005$37,500.00$187.50
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.995 0.990.005$14,950.00$74.75
14TRAFFIC CONTROL1.00LS 0.995 0.990.005$9,375.00$46.88
20ELECTRICAL1.00LS 0.87 0.860.01$487,566.00$4,875.66
22MECHANICAL DEMOLITION1.00LS 1.00 0.910.09$29,875.00$2,688.75
24AXIAL FLOW PUMPS1.00LS 0.9887 0.92460.0641$1,908,750.00$122,350.88
31TEMPORARY BYPASS1.00LS 0.80 0.600.20$59,925.00$11,985.00
S-3APLUG TRANSITION STRUCTURE LS 0.50 0.000.50$13,500.00$6,750.00
S-5AXIAL FLOW PUMP ANCHORAGE LS 1.00 0.660.34$38,700.00$13,158.00
S-13REPLACE LEVEL TRANSMITTER LS 1.00 0.001.00$6,000.00$6,000.00
S-14PLATE WALL ADAPTER ANCHOR RELOCATION LS 0.80 0.000.80$3,900.00$3,120.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 362.10 116.11245.99$1.00 $245.99

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,266,926.38 $4,095,126.46 $171,799.92
Retained $213,346.32 $204,756.33 $8,589.99
Deducted $362.10 $116.11 $245.99
Due $4,053,217.96 $3,890,254.02 $162,963.94



Contact Office Engineer
Contractor Copy  