| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.40 | 0.20 | $22,137.00 | $4,427.40 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.60
| 0.40 | 0.20 | $7,379.00 | $1,475.80 |
| 8 | IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND COLLECTION PLAN | 1.00 | LS |
1.00
| 0.50 | 0.50 | $11,069.00 | $5,534.50 |
| 10 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.40 | 0.20 | $29,517.00 | $5,903.40 |
| 11 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.40 | 0.20 | $11,069.00 | $2,213.80 |
| 12 | OFFICE FACILITIES | 6.00 | MTH |
3.00
| 2.00 | 1.00 | $1,181.00 | $1,181.00 |
| 24 | IMPLEMENTATION OF TEMPORARY BYPASS | 1.00 | LS |
0.90
| 0.75 | 0.15 | $27,095.00 | $4,064.25 |