Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Marie Canyon Stormwater Disinfection System Upgrade
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001374
Federal Number(s): None
Original Contract: $1,646,300.00
Awarded: 4/15/2025
Period Ending: 6/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 4.00 3.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.60 0.400.20$22,137.00$4,427.40
6IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.60 0.400.20$7,379.00$1,475.80
8IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND COLLECTION PLAN1.00LS 1.00 0.500.50$11,069.00$5,534.50
10TRAFFIC CONTROL1.00LS 0.60 0.400.20$29,517.00$5,903.40
11IMPLEMENTATION OF THE LTWHP1.00LS 0.60 0.400.20$11,069.00$2,213.80
12OFFICE FACILITIES6.00MTH 3.00 2.001.00$1,181.00$1,181.00
24IMPLEMENTATION OF TEMPORARY BYPASS1.00LS 0.90 0.750.15$27,095.00$4,064.25

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $394,910.32 $369,610.17 $25,300.15
Retained $19,745.52 $18,480.51 $1,265.01
Deducted $2,000.00 $2,000.00 $0.00
Due $373,164.80 $349,129.66 $24,035.14



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.