| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 9.00 | MTH |
7.00
| 6.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.70
| 0.60 | 0.10 | $8,000.00 | $800.00 |
| 8 | IMPLEMENTATION OF THE NOISE MITIGATION PLAN | 1.00 | LS |
1.00
| 0.70 | 0.30 | $16,500.00 | $4,950.00 |
| 10 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.70
| 0.60 | 0.10 | $35,000.00 | $3,500.00 |
| 11 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.80 | 0.20 | $2,000.00 | $400.00 |
| 15 | OFFICE FACILITIES | 10.00 | MTH |
7.00
| 6.00 | 1.00 | $3,000.00 | $3,000.00 |
| 43 | MASONRY BLOCK WALL | 804.00 | LF |
786.00
| 777.00 | 9.00 | $303.00 | $2,727.00 |
| 53 | WELL SLAB AND PEDESTAL PER STD PLAN W-20 | 1.00 | LS |
1.00
| 0.00 | 1.00 | $36,000.00 | $36,000.00 |
| 54 | DISINFECTION OF WELL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,750.00 | $2,750.00 |
| 58 | 8" FLG'D GATE VALVE, CL 125, 200 PSI, WWP, NRS, WITH VALVE BOX PER LACWD STD PLAN W-15 | 6.00 | EA |
6.00
| 3.00 | 3.00 | $7,720.00 | $23,160.00 |
| 61 | 8" WATERMAIN, D.I. | 1,016.00 | LF |
989.00
| 985.00 | 4.00 | $216.00 | $864.00 |
| 63 | 8" CML STL PIPE, 0.25" WALL THICKNESS (WELL 4-91) | 25.00 | LF |
25.00
| 19.00 | 6.00 | $4,025.00 | $24,150.00 |
| 68 | ORNAMENTAL STEEL FENCE | 68.00 | LF |
68.00
| 0.00 | 68.00 | $605.00 | $41,140.00 |
| 70 | VIDEO INSPECTION | 1.00 | LS |
1.00
| 0.50 | 0.50 | $3,500.00 | $1,750.00 |
| 71 | STRUCTURE CONCRETE | 121.00 | CY |
121.00
| 56.00 | 65.00 | $1,200.00 | $78,000.00 |
| 72 | GRAVEL PAVEMENT | 14,200.00 | SF |
12,200.00
| 4,800.00 | 7,400.00 | $2.50 | $18,500.00 |
| 73 | ELECTRICAL WORK | 1.00 | LS |
0.6028
| 0.3639 | 0.2389 | $1,049,721.00 | $250,778.35 |
| 75 | WELL PUMP AND MOTOR | 1.00 | LS |
1.00
| 0.00 | 1.00 | $211,200.00 | $211,200.00 |
| S-2 | STAINLESS STEEL AIRLINE W/ PRESSURE GAUGE | | LS |
1.00
| 0.00 | 1.00 | $2,121.00 | $2,121.00 |
| S-4 | 8 INCH WELL SURFACE PLATE | | LS |
1.00
| 0.00 | 1.00 | $7,413.00 | $7,413.00 |
| S-5 | GRAVEL PAVEMENT W/ HEADER | | LS |
1.00
| 0.00 | 1.00 | $31,939.00 | $31,939.00 |
| S-7 | WELL PUMP EXTENSION | | LS |
1.00
| 0.00 | 1.00 | $30,663.00 | $30,663.00 |
| S-8 | DISCHARGE PIPE RE-COATING | | LS |
1.00
| 0.00 | 1.00 | $9,545.00 | $9,545.00 |
|