Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Florence Neighborhood Mobility (AHSC)
Contractor: Toro Enterprises, Inc.
P.O. Box 6285
Oxnard, CA 93031
Project ID: RDC0016428
Federal Number(s): None
Original Contract: $4,441,362.76
Awarded: 11/7/2025
Period Ending: 6/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)12.00MTH 4.00 3.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.50 0.3750.125$35,000.00$4,375.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.50 0.3750.125$90,000.00$11,250.00
7OFFICE FACILITIES12.00MTH 4.00 3.001.00$6,900.00$6,900.00
9CLEARING AND GRUBBING1.00LS 1.00 0.750.25$21,000.00$5,250.00
16CONCRETE REMOVAL (NON-REINFORCED)304.00CY 304.00 257.0047.00$435.00$20,445.00
17UNCLASSIFIED EXCAVATION3,383.00CY 2,600.00 2,101.21498.79$130.00$64,842.70
19CRUSHED MISCELLANEOUS BASE1,971.00CY 1,230.89 876.34354.55$105.00$37,227.75
21TRENCH BACKFILL SLURRY (CLASS 270-E-500)29.00CY 20.00 12.008.00$385.00$3,080.00
25AC PAVEMENT (PATCHBACK)889.00SF 728.50 440.00288.50$10.00$2,885.00
30PCC PAVEMENT111.00CY 81.51 46.6634.85$460.00$16,031.00
35PCC CURB, TYPE A1-VAR91.00LF 91.00 17.5073.50$65.00$4,777.50
36PCC CURB & GUTTER, TYPE A2-VAR2,174.00LF 1,342.87 964.72378.15$75.00$28,361.25
37PCC WALK, 4" THICK24,108.00SF 16,798.87 12,806.553,992.32$11.55$46,111.30
38PCC CURB RAMPS71.00CY 57.03 47.189.85$2,400.00$23,640.00
39DETECTABLE WARNING SURFACE824.00SF 561.40 431.80129.60$32.00$4,147.20
40CROSS GUTTER56.00CY 56.00 34.1621.84$785.00$17,144.40
46NO. 6 PULL BOX INCL PCC COVER11.00EA 5.00 4.001.00$2,510.00$2,510.00
47INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT3,150.00LF 650.00 0.00650.00$22.50$14,625.00
49REMOVE PULL BOX AND RESURFACE SIDEWALK9.00EA 1.00 0.001.00$560.00$560.00
59REMOVE TYPE 1 FOUNDATION5.00EA 3.00 0.003.00$1,442.00$4,326.00
61REMOVE TYPE 19 FOUNDATION3.00EA 1.00 0.001.00$2,405.00$2,405.00
77STREET LIGHTING STANDARD (COMPLETE)2.00EA 2.00 0.002.00$4,900.00$9,800.00
79TYPE 1 STANDARD FOUNDATION2.00EA 1.00 0.001.00$4,343.45$4,343.45
80TYPE 15 STANDARD FOUNDATION5.00EA 2.00 0.002.00$4,834.95$9,669.90
95PAVEMENT MARKINGS (THERMOPLASTIC)961.00SF 400.00 268.00132.00$9.30$1,227.60
9712" STRIPING (THERMOPLASTIC)1,251.00LF 225.00 114.50110.50$6.10$674.05
99REMOVE STRIPING400.00LF 165.00 0.00165.00$2.00$330.00
100REMOVE PAVEMENT MARKING4,337.00SF 45.00 0.0045.00$3.20$144.00
107RELOCATE SIGN50.00EA 16.00 11.005.00$160.00$800.00
109RELOCATE SIGN POST18.00EA 15.00 11.004.00$265.00$1,060.00
114DETAIL 21 (THERMOPLASTIC)1,329.00LF 553.00 344.00209.00$1.90$397.10
117DETAIL 31 (THERMOPLASTIC)532.00LF 152.00 100.0052.00$2.40$124.80
12124" STRIPING (THERMOPLASTIC)8,520.00LF 2,182.50 1,517.50665.00$8.90$5,918.50
S-13CURB DRAINS AT 68TH & PARMELEE T&M 20,944.00 0.0020,944.00$1.00$20,944.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,699,502.48 $2,322,674.98 $376,827.50
Retained $134,975.12 $116,133.75 $18,841.37
Deducted $0.00 $0.00 $0.00
Due $2,564,527.36 $2,206,541.23 $357,986.13



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.