| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.50
| 0.375 | 0.125 | $35,000.00 | $4,375.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.50
| 0.375 | 0.125 | $90,000.00 | $11,250.00 |
| 7 | OFFICE FACILITIES | 12.00 | MTH |
4.00
| 3.00 | 1.00 | $6,900.00 | $6,900.00 |
| 9 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.75 | 0.25 | $21,000.00 | $5,250.00 |
| 16 | CONCRETE REMOVAL (NON-REINFORCED) | 304.00 | CY |
304.00
| 257.00 | 47.00 | $435.00 | $20,445.00 |
| 17 | UNCLASSIFIED EXCAVATION | 3,383.00 | CY |
2,600.00
| 2,101.21 | 498.79 | $130.00 | $64,842.70 |
| 19 | CRUSHED MISCELLANEOUS BASE | 1,971.00 | CY |
1,230.89
| 876.34 | 354.55 | $105.00 | $37,227.75 |
| 21 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 29.00 | CY |
20.00
| 12.00 | 8.00 | $385.00 | $3,080.00 |
| 25 | AC PAVEMENT (PATCHBACK) | 889.00 | SF |
728.50
| 440.00 | 288.50 | $10.00 | $2,885.00 |
| 30 | PCC PAVEMENT | 111.00 | CY |
81.51
| 46.66 | 34.85 | $460.00 | $16,031.00 |
| 35 | PCC CURB, TYPE A1-VAR | 91.00 | LF |
91.00
| 17.50 | 73.50 | $65.00 | $4,777.50 |
| 36 | PCC CURB & GUTTER, TYPE A2-VAR | 2,174.00 | LF |
1,342.87
| 964.72 | 378.15 | $75.00 | $28,361.25 |
| 37 | PCC WALK, 4" THICK | 24,108.00 | SF |
16,798.87
| 12,806.55 | 3,992.32 | $11.55 | $46,111.30 |
| 38 | PCC CURB RAMPS | 71.00 | CY |
57.03
| 47.18 | 9.85 | $2,400.00 | $23,640.00 |
| 39 | DETECTABLE WARNING SURFACE | 824.00 | SF |
561.40
| 431.80 | 129.60 | $32.00 | $4,147.20 |
| 40 | CROSS GUTTER | 56.00 | CY |
56.00
| 34.16 | 21.84 | $785.00 | $17,144.40 |
| 46 | NO. 6 PULL BOX INCL PCC COVER | 11.00 | EA |
5.00
| 4.00 | 1.00 | $2,510.00 | $2,510.00 |
| 47 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 3,150.00 | LF |
650.00
| 0.00 | 650.00 | $22.50 | $14,625.00 |
| 49 | REMOVE PULL BOX AND RESURFACE SIDEWALK | 9.00 | EA |
1.00
| 0.00 | 1.00 | $560.00 | $560.00 |
| 59 | REMOVE TYPE 1 FOUNDATION | 5.00 | EA |
3.00
| 0.00 | 3.00 | $1,442.00 | $4,326.00 |
| 61 | REMOVE TYPE 19 FOUNDATION | 3.00 | EA |
1.00
| 0.00 | 1.00 | $2,405.00 | $2,405.00 |
| 77 | STREET LIGHTING STANDARD (COMPLETE) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $4,900.00 | $9,800.00 |
| 79 | TYPE 1 STANDARD FOUNDATION | 2.00 | EA |
1.00
| 0.00 | 1.00 | $4,343.45 | $4,343.45 |
| 80 | TYPE 15 STANDARD FOUNDATION | 5.00 | EA |
2.00
| 0.00 | 2.00 | $4,834.95 | $9,669.90 |
| 95 | PAVEMENT MARKINGS (THERMOPLASTIC) | 961.00 | SF |
400.00
| 268.00 | 132.00 | $9.30 | $1,227.60 |
| 97 | 12" STRIPING (THERMOPLASTIC) | 1,251.00 | LF |
225.00
| 114.50 | 110.50 | $6.10 | $674.05 |
| 99 | REMOVE STRIPING | 400.00 | LF |
165.00
| 0.00 | 165.00 | $2.00 | $330.00 |
| 100 | REMOVE PAVEMENT MARKING | 4,337.00 | SF |
45.00
| 0.00 | 45.00 | $3.20 | $144.00 |
| 107 | RELOCATE SIGN | 50.00 | EA |
16.00
| 11.00 | 5.00 | $160.00 | $800.00 |
| 109 | RELOCATE SIGN POST | 18.00 | EA |
15.00
| 11.00 | 4.00 | $265.00 | $1,060.00 |
| 114 | DETAIL 21 (THERMOPLASTIC) | 1,329.00 | LF |
553.00
| 344.00 | 209.00 | $1.90 | $397.10 |
| 117 | DETAIL 31 (THERMOPLASTIC) | 532.00 | LF |
152.00
| 100.00 | 52.00 | $2.40 | $124.80 |
| 121 | 24" STRIPING (THERMOPLASTIC) | 8,520.00 | LF |
2,182.50
| 1,517.50 | 665.00 | $8.90 | $5,918.50 |
| S-13 | CURB DRAINS AT 68TH & PARMELEE | | T&M |
20,944.00
| 0.00 | 20,944.00 | $1.00 | $20,944.00 |
|