| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | PREPARATION OF THE WATERLINE DISCHARGE PLAN (STIPULATED PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 6 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $15,000.00 | $3,000.00 |
| 7 | INSTALLATION OF ESA FENCING | 890.00 | LF |
890.00
| 0.00 | 890.00 | $25.00 | $22,250.00 |
| 8 | MAINTENANCE AND REMOVAL OF ESA FENCING | 890.00 | LF |
178.00
| 0.00 | 178.00 | $10.00 | $1,780.00 |
| 9 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.75
| 0.00 | 0.75 | $35,000.00 | $26,250.00 |
| 10 | OFFICE FACILITIES | 6.00 | MTH |
1.33
| 0.00 | 1.33 | $5,000.00 | $6,650.00 |
| 11 | MOBILIZATION | 1.00 | LS |
0.75
| 0.00 | 0.75 | $75,000.00 | $56,250.00 |
| 12 | CLEARING AND GRUBBING | 1.00 | LS |
0.90
| 0.00 | 0.90 | $35,000.00 | $31,500.00 |
| 14 | INSTALL 18" STEEL WATERMAIN, CML&C, WELDED (DELIVER FROM POINT DUME YARD) | 100.00 | LF |
33.00
| 0.00 | 33.00 | $1,000.00 | $33,000.00 |
| 17 | FLEXIBLE EXPANSION JOINT, DOUBLE BALL, 18" | 2.00 | EA |
1.20
| 0.00 | 1.20 | $50,000.00 | $60,000.00 |
| 26 | RELOCATE RIP RAP | 5.00 | CY |
3.00
| 0.00 | 3.00 | $1,000.00 | $3,000.00 |
| 27 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.00 | 0.40 | $35,000.00 | $14,000.00 |
| S-1 | EXTEND NTP PART 1 DURATION | | WD |
2.00
| 0.00 | 2.00 | $0.00 | $0.00 |