Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: South Street TSSP - Atlantic Avenue to Studebaker Road
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TSM0010286
Federal Number(s): None
Original Contract: $687,441.00
Awarded: 7/15/2025
Period Ending: 6/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)7.00MTH 4.00 3.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.78 0.530.25$1,500.00$375.00
7TRAFFIC CONTROL1.00LS 0.78 0.530.25$19,000.00$4,750.00
122-PAIR DETECTOR LEAD-IN CABLE1,225.00LF 1,225.00 0.001,225.00$3.00$3,675.00
1328-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)715.00LF 715.00 0.00715.00$10.00$7,150.00
15#8 WIRE930.00LF 930.00 0.00930.00$2.70$2,511.00
22REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.)3.00EA 3.00 0.003.00$612.00$1,836.00
23REMOVE TYPE 17 STANDARD (COMPLETE) (EXCL. FOUND.)1.00EA 1.00 0.001.00$1,426.00$1,426.00
26REMOVE SIGNAL 20' MAST ARM4.00EA 4.00 0.004.00$600.00$2,400.00
27REMOVE VEHICLE HEAD (COMPLETE)18.00EA 18.00 17.001.00$200.00$200.00
28REMOVE PEDESTRIAN PUSH BUTTON3.00EA 1.00 0.001.00$100.00$100.00
29REMOVE PED PUSH BUTTON AND COLD WELD HOLE TO SMOOTH FINISH1.00EA 1.00 0.001.00$125.00$125.00
31REMOVE TYPE 1 FOUNDATION3.00EA 3.00 0.003.00$1,000.00$3,000.00
33REMOVE TYPE 17 FOUNDATION1.00EA 1.00 0.001.00$1,900.00$1,900.00
36RELOCATE VEHICLE HEAD (COMPLETE)4.00EA 4.00 0.004.00$600.00$2,400.00
51TYPE 1 STANDARD3.00EA 3.00 2.001.00$2,175.00$2,175.00
52TYPE 15 STANDARD2.00EA 2.00 1.001.00$7,500.00$7,500.00
53TYPE 19 STANDARD3.00EA 2.00 0.002.00$12,400.00$24,800.00
54TYPE 19 STANDARD WITH MODIFIED 21' HIGH POLE1.00EA 1.00 0.001.00$12,400.00$12,400.00
6225' SIGNAL MAST ARM1.00EA 1.00 0.001.00$3,550.00$3,550.00
6330' SIGNAL MAST ARM7.00EA 6.00 0.006.00$4,365.00$26,190.00
6412' LUMINAIRE MAST ARM6.00EA 5.00 0.005.00$2,100.00$10,500.00
658' STRAIGHT MAST ARM FOR SNS1.00EA 1.00 0.001.00$2,752.00$2,752.00
66PEDESTRIAN PUSH BUTTON8.00EA 7.00 0.007.00$2,884.00$20,188.00
67PEDESTRIAN PUSH BUTTON PLATE8.00EA 7.00 0.007.00$35.00$245.00
68PEDESTRIAN PUSH BUTTON POST1.00EA 1.00 0.001.00$2,110.00$2,110.00
703-12" LED VEHICLE HEAD (COMPLETE) 24.00EA 23.00 13.0010.00$1,617.00$16,170.00
715-12" LED VEHICLE HEAD (COMPLETE) 15.00EA 14.00 5.009.00$2,049.00$18,441.00
72SALVAGE EQUIPMENT1.00LS 1.00 0.250.75$8,153.00$6,114.75
S-4INSTALL PELCO BRACKET - CO #4 LS 1.00 0.001.00$3,770.37$3,770.37
S-7INSTALL 5- CONDUCTOR LF 1,615.00 0.001,615.00$4.05$6,540.75

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $583,334.84 $387,539.97 $195,794.87
Retained $29,166.74 $19,377.00 $9,789.74
Deducted $0.00 $0.00 $0.00
Due $554,168.10 $368,162.97 $186,005.13



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.