As-Built 10
Project Name: Bridge Preventive Maintenance Program - Group 16 Cities
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0015922
Federal Number(s): BPMPL-5953(726)
Original Contract: $2,210,300.00
Awarded: 5/20/2024
Period Ending: 7/7/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 2.00 2.000.00$500.00$0.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
4PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 1.000.00$5,000.00$0.00
5IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 1.00 1.000.00$10,000.00$0.00
6IMPLEMENTATION OF THE LTWHP1.00LS 1.00 1.000.00$25,000.00$0.00
7ENVIRONMENTAL AIR MONITORING1.00LS 1.00 1.000.00$15,000.00$0.00
8PREPARATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 1.00 1.000.00$10,000.00$0.00
10PREPARATION OF THE DEBRIS CONTAINMENT AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 1.000.00$2,500.00$0.00
11IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND CONTROL PLAN1.00LS 1.00 1.000.00$30,000.00$0.00
12CITIES PERMIT AND INSPECTION FEES (ALLOWANCE OF $16,000)16,000.00AL 490.00 490.000.00$1.00$0.00
13OFFICE FACILITIES4.00MTH 4.00 4.000.00$15,000.00$0.00
14ADDITIONAL DECK AND SPALL REPAIRS (ALLOWANCE OF $48,000)48,000.00AL 19,205.18 19,205.180.00$1.00$0.00
15SAWCUT GROOVES FOR JOINT SEAL (ALLOWANCE OF $8,000)8,000.00AL 0.00 0.000.00$1.00$0.00
16TRAFFIC CONTROL1.00LS 1.00 1.000.00$228,771.00$0.00
17FLASHING ARROW SIGN1.00LS 1.00 1.000.00$5,000.00$0.00
18CHANGEABLE MESSAGE SIGN1.00LS 1.00 1.000.00$50,000.00$0.00
19TEMPORARY RAILING (TYPE K)430.00LF 400.00 400.000.00$65.00$0.00
20BRIDGE REMOVAL (PORTIONS)1.00LS 1.00 1.000.00$175,000.00$0.00
21STRUCTURE CONCRETE3.00CY 3.00 3.000.00$45,000.00$0.00
22BAR REINFORCING STEEL157.00LB 157.00 157.000.00$35.00$0.00
23DECK DRAIN3.00EA 3.00 3.000.00$12,000.00$0.00
24MISCELLANEOUS METAL (BRIDGE)2,645.00LB 2,912.00 2,912.000.00$50.00$0.00
25CLEAN & PAINT STRUCTURAL STEEL1.00LS 1.00 1.000.00$150,000.00$0.00
26CHAIN LINK FENCE, 5' HIGH16.00LF 16.00 16.000.00$450.00$0.00
27REMOVE DETAIL 9 (PAINT)1,933.00LF 1,933.00 1,933.000.00$1.00$0.00
28DETAIL 9 (THERMOPLASTIC)1,933.00LF 1,933.00 1,933.000.00$2.00$0.00
29REMOVE DETAIL 21 (YELLOW PAINT)204.00LF 204.00 204.000.00$7.00$0.00
30DETAIL 21 (THERMOPLASTIC)204.00LF 204.00 204.000.00$6.00$0.00
31REMOVE DETAIL 22 (YELLOW PAINT)674.00LF 674.00 674.000.00$7.00$0.00
32DETAIL 22 (THERMOPLASTIC)674.00LF 674.00 674.000.00$3.00$0.00
33REMOVE DETAIL 27B (PAINT)755.00LF 755.00 755.000.00$3.00$0.00
34DETAIL 27B (THERMOPLASTIC)755.00LF 755.00 755.000.00$3.00$0.00
35REMOVE DETAIL 29 (YELLOW PAINT)755.00LF 380.00 380.000.00$7.00$0.00
36DETAIL 29 (THERMOPLASTIC)755.00LF 380.00 380.000.00$3.00$0.00
37REMOVE 12" STRIPING (PAINT)415.00LF 425.00 415.0010.00$7.00$70.00
3812" STRIPING (THERMOPLASTIC)415.00LF 382.00 382.000.00$9.00$0.00
39REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DECK)358.00SF 320.00 320.000.00$185.00$0.00
40REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (SIDEWALK)33.00SF 26.00 26.000.00$685.00$0.00
41REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (BARRIER)73.00SF 87.00 73.0014.00$330.00$4,620.00
42REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (SOFFIT)7.00SF 7.00 7.000.00$1,650.00$0.00
43REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (ABUTMENT)66.00SF 63.00 63.000.00$310.00$0.00
44REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (PIER)33.00SF 33.00 33.000.00$1,080.00$0.00
45REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DIAPHRAGM)22.00SF 22.00 22.000.00$1,350.00$0.00
46REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (GIRDER)467.00SF 467.00 467.000.00$235.00$0.00
47RAPID SETTING CONCRETE PATCH (DECK)358.00SF 320.00 320.000.00$235.00$0.00
48REPAIR SPALLED CONCRETE (SIDEWALK)33.00SF 26.00 26.000.00$715.00$0.00
49REPAIR SPALLED CONCRETE (BARRIER)73.00SF 87.00 73.0014.00$360.00$5,040.00
50REPAIR SPALLED CONCRETE (SOFFIT)7.00SF 7.00 7.000.00$1,325.00$0.00
51REPAIR SPALLED CONCRETE (ABUTMENT)66.00SF 63.00 63.000.00$360.00$0.00
52REPAIR SPALLED CONCRETE (PIER)33.00SF 33.00 33.000.00$1,115.00$0.00
53REPAIR SPALLED CONCRETE (DIAPHRAGM)22.00SF 22.00 22.000.00$1,365.00$0.00
54REPAIR SPALLED CONCRETE (GIRDER)467.00SF 467.00 467.000.00$280.00$0.00
55PREPARE CONCRETE DECK SURFACE66,907.00SF 66,907.00 66,907.000.00$1.00$0.00
56TREAT BRIDGE DECK66,907.00SF 66,907.00 66,907.000.00$1.00$0.00
57BRIDGE DECK TREATMENT MATERIAL836.00GAL 677.00 677.000.00$70.00$0.00
58CLEAN EXPANSION JOINT874.00LF 868.00 868.000.00$30.00$0.00
59JOINT SEAL (MR 1/2")185.00LF 197.00 185.0012.00$120.00$1,440.00
60JOINT SEAL (MR 1")105.00LF 0.00 0.000.00$140.00$0.00
61JOINT SEAL (MR 1-1/2")80.00LF 74.00 74.000.00$230.00$0.00
62JOINT SEAL, TYPE AL504.00LF 504.00 504.000.00$56.00$0.00
S-1TC ON ROSECRANS/SGR BIKE PATH T&M 4,172.20 4,172.200.00$1.00$0.00
S-2INSTALLATION OF SLED TYPE 2 ATTENUATOR AND TEMPORARY FENCING ON ARTESIA BLVD LS 1.00 1.000.00$17,821.25$0.00
S-3TYPE B JOINT SEAL PIER 3 AT WHITTIER BLVD LS 1.00 1.000.00$7,839.22$0.00
S-4REMOVE UNSOUND CONCRETE (CO #5) SF 70.00 70.000.00$330.00$0.00
S-5SPALL REPAIR BARRIER RAIL N/SIDE (CO #5) SF 70.00 70.000.00$360.00$0.00
S-6TRAFFIC CONTROL/MOBILIZATION (CO #6) LS 1.00 1.000.00$20,000.00$0.00
S-7CHANGEABLE MESSAGE SIGN (CO #6) LS 1.00 1.000.00$5,000.00$0.00
S-8STRUCTURE CONCRETE REPAIR ADJACENT DIAPHRAGM (CO #6) LS 1.00 1.000.00$15,000.00$0.00
S-9MISCELLANEOUS METAL - BRIDGE (CO #6) LB 1,250.00 1,250.000.00$50.00$0.00
S-10CLEAN AND PAINT STRUCTURAL STEEL (CO #6) LS 1.00 1.000.00$18,000.00$0.00
S-11STRUCTURE CONCRETE (CO #7) CY 7.50 7.500.00$10,000.00$0.00
S-12BAR REINFORCING STEEL (CO #7) LB 1,320.00 1,320.000.00$15.00$0.00
S-13DRILL AND BOND DOWELS (CO #7) LB 40.00 40.000.00$100.00$0.00
S-14JOINT SEAL - MR 1-1/2" (CO #7) LF 60.00 60.000.00$280.00$0.00
S-15EPOXY INJECTION AND SPALL REPAIR PIER 2 (CO #8) LS 0.00 0.000.00$50,000.00$0.00
S-16DRILL AND BOND DOWELS (CO #8) LF 0.00 0.000.00$100.00$0.00
S-17BRIDGE REMOVAL (PORTIONS) - CONCRETE REMOVAL (CO #8) LS 0.00 0.000.00$43,000.00$0.00
S-18REINFORCING BARS (CO #9) LF 0.00 0.000.00$30.00$0.00
S-19CONCRETE REMOVAL (CO #9) CY 0.00 0.000.00$15,000.00$0.00
S-20THREADED RODS, BOLTS, NUTS (CO #9) LB 0.00 0.000.00$300.00$0.00
S-21STRUCTURE CONCRETE (CO #9) CY 0.00 0.000.00$40,000.00$0.00
S-22CONTRACT TIME EXTENSION (CO #10) WD 273.00 0.00273.00$0.00$0.00
S-23SPALL REPAIR & UNSOUND CONCRETE REMOVAL (DIFFERENCE IN UNIT PRICE CORRECTION PER CO #5) LS 1.00 0.001.00($7,700.00)($7,700.00)

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 0.00 0.000.00$0.00 $0.00
LIQUIDATED DAMAGESDAY 0.00 0.000.00$2,000.00 $0.00
LABOR COMPLIANCEVIOLATION 0.00 0.000.00$0.00 $0.00
AFFIRMATIVE ACTIONVIOLATION 0.00 0.000.00$0.00 $0.00
BEST MANAGEMENT PRACTICEVIOLATION 0.00 0.000.00$1,000.00 $0.00
SCHEDULE UPDATEMONTHLY 0.00 0.000.00$0.00 $0.00
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 0.00 0.000.00$0.00 $0.00
EXHIBIT 16-Z11 0.00 0.000.00$1,000.00 $0.00
EXHIBIT 9-P1 0.00 0.000.00$1,000.00 $0.00
LABOR COMPLIANCE1 0.00 0.000.00$27,374.43 $0.00
LOCAL TARGETED WORKER HIRING PROGRAMVIOLATION 3,436.75 3,436.750.00$1.00 $0.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,427,390.85 $2,422,920.85 $4,470.00
Retained $60,684.77 $60,573.02 $111.75
Deducted $3,436.75 $3,436.75 $0.00
Due $2,363,269.33 $2,358,911.08 $4,358.25



*The term "As-Built" used by the Department of Public Works in combination with the Engineer's Monthly Estimate process indicates that the project has been field accepted and that the pay quantities and deductions as detailed above are FINAL. Unless a certified letter is received by this office within 14 calendar days disputing the amounts shown, an acceptance letter will be filed with the Board of Supervisors authorizing the release of retention.