| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.80
| 0.60 | 0.20 | $22,137.00 | $4,427.40 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.80
| 0.60 | 0.20 | $7,379.00 | $1,475.80 |
| 9 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $23,613.00 | $5,903.25 |
| 10 | TRAFFIC CONTROL | 1.00 | LS |
0.80
| 0.60 | 0.20 | $29,517.00 | $5,903.40 |
| 11 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.60 | 0.20 | $11,069.00 | $2,213.80 |
| 12 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $1,181.00 | $1,181.00 |
| 14 | MISCELLANEOUS MECHANICAL WORK | 1.00 | LS |
0.52
| 0.00 | 0.52 | $66,707.00 | $34,687.64 |
| 15 | ELECTRICAL WORK | 1.00 | LS |
0.55
| 0.144 | 0.406 | $472,583.00 | $191,868.70 |
| S-3 | GAC FILTRATION SYSTEM | | LS |
0.80
| 0.00 | 0.80 | $701,614.00 | $561,291.20 |
| S-5 | FIELD OFFICE CREDIT | | LS |
1.00
| 0.00 | 1.00 | ($1,500.00) | ($1,500.00) |
| S-7 | DRILLING AND SKID REMOVAL | | T&M |
1.00
| 0.00 | 1.00 | $1.00 | $1.00 |
| S-9 | K-RAIL CREDIT | | LS |
1.00
| 0.00 | 1.00 | ($1,800.00) | ($1,800.00) |