| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.33
| 0.00 | 0.33 | $15,000.00 | $4,950.00 |
| 5 | PREPARATION OF THE DIVERSION OF WATER PLAN (STIPULATED UNIT PRICE OF $3,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 7 | PREPARATION OF THE EMERGENCY EVACUATION PLAN (STIPULATED UNIT PRICE OF $1,500) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $1,500.00 | $750.00 |
| 8 | PREPARATION OF THE FIRE PREVENTION PLAN (STIPULATED UNIT PRICE OF $1,500) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $1,500.00 | $750.00 |
| 9 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.80
| 0.00 | 0.80 | $35,000.00 | $28,000.00 |
| 10 | MOBILIZATION | 1.00 | LS |
0.95
| 0.00 | 0.95 | $50,000.00 | $47,500.00 |
| 11 | CLEARING AND GRUBBING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $50,000.00 | $25,000.00 |
| 12 | REMOVE EXISTING CHAIN LINK FENCE | 25.00 | LF |
25.00
| 0.00 | 25.00 | $50.00 | $1,250.00 |
| 13 | CONCRETE REMOVAL (REINFORCED) | 29.00 | CY |
29.00
| 0.00 | 29.00 | $650.00 | $18,850.00 |
| 14 | STRUCTURE EXCAVATION | 33.00 | CY |
33.00
| 0.00 | 33.00 | $250.00 | $8,250.00 |
| 34 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.00 | 0.50 | $16,500.00 | $8,250.00 |
| 37 | REMOVE AND REINSTALL GUARDRAIL | 1.00 | LS |
0.50
| 0.00 | 0.50 | $6,500.00 | $3,250.00 |
| 38 | LEAN CONCRETE REMOVAL | 29.00 | CY |
29.00
| 0.00 | 29.00 | $200.00 | $5,800.00 |
| 39 | REMOVE UNSOUND CONCRETE (RETAINING WALL) | 97.00 | SF |
97.00
| 0.00 | 97.00 | $85.00 | $8,245.00 |
| 40 | REMOVE AND DISPOSE OF EXISTING 30" HDPE PIPE | 1.00 | LS |
0.50
| 0.00 | 0.50 | $8,000.00 | $4,000.00 |
| S-1 | EXTEND PART 1 NTP DURATION - 5 DAYS | | LS |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |