Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: South Street TSSP - Atlantic Avenue to Studebaker Road
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TSM0010286
Federal Number(s): None
Original Contract: $687,441.00
Awarded: 7/15/2025
Period Ending: 7/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)7.00MTH 5.00 4.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 1.00 0.780.22$1,500.00$330.00
7TRAFFIC CONTROL1.00LS 1.00 0.780.22$19,000.00$4,180.00
20REMOVE CONTROLLER3.00EA 3.00 0.003.00$200.00$600.00
46TYPE 332 CABINET1.00EA 1.00 0.001.00$34,500.00$34,500.00
73DETAIL 41 (THERMOPLASTIC)70.00LF 65.00 0.0065.00$8.00$520.00
74CURB MARKINGS (ONE-COAT PAINT)70.00LF 70.00 0.0070.00$5.20$364.00
S-1SCE APPLICATION FEE (CO #1) NEG 6,954.92 0.006,954.92$1.00$6,954.92
S-8LONG BEACH LIST OF WORK - SIGNAGE (CO #8) LS 0.85 0.000.85$30,571.20$25,985.52
S-9LONG BEACH LIST OF WORK - LOOP (CO #9) LS 1.00 0.001.00$43,806.01$43,806.01
S-10CITY OF LONG BEACH LIST OF WORK - RELOCATE TS EQUIPMENT (CO #10)  LS 1.00 0.001.00$30,145.41$30,145.41

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $731,220.70 $583,334.84 $147,885.86
Retained $36,561.04 $29,166.74 $7,394.30
Deducted $0.00 $0.00 $0.00
Due $694,659.66 $554,168.10 $140,491.56



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.