| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
11.00
| 10.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.76
| 0.68 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
11.00
| 10.00 | 1.00 | $4,000.00 | $4,000.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
204.50
| 184.50 | 20.00 | $1,800.00 | $36,000.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.76
| 0.68 | 0.08 | $34,000.00 | $2,720.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
11.00
| 10.00 | 1.00 | $5,000.00 | $5,000.00 |
| 28 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.50 | 0.50 | $35,000.00 | $17,500.00 |
| 38 | PERMEABLE ZONE MATERIAL | 2,691.00 | CY |
1,140.00
| 1,040.00 | 100.00 | $80.00 | $8,000.00 |
| 39 | BUTTRESS FILL | 16,505.00 | CY |
14,577.10
| 13,717.10 | 860.00 | $55.00 | $47,300.00 |
| 40 | DOWNSTREAM RIPRAP (CLASS IV) | 7,571.00 | CY |
4,904.94
| 4,571.79 | 333.15 | $75.00 | $24,986.25 |
| 42 | CRUSHED ROCK | 3,548.00 | CY |
3,548.00
| 3,404.32 | 143.68 | $200.00 | $28,736.00 |
| 50 | 48" RCP & APPURTENANCES | 150.00 | LF |
109.00
| 101.00 | 8.00 | $720.00 | $5,760.00 |
| 72 | TOE DRAIN WEIR VAULT | 1.00 | LS |
0.05
| 0.00 | 0.05 | $22,000.00 | $1,100.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.86
| 0.76 | 0.10 | $6,000,000.00 | $600,000.00 |
| 75 | INTAKE TOWER COMPLETE IN PLACE | 1.00 | LS |
0.56
| 0.33 | 0.23 | $1,500,000.00 | $345,000.00 |
| 77 | INTAKE TOWER TRASH RACK COMPLETE IN PLACE | 1.00 | LS |
0.90
| 0.80 | 0.10 | $445,000.00 | $44,500.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.62
| 0.54 | 0.08 | $700,000.00 | $56,000.00 |
| 81 | INTAKE TOWER GATE & ACTUATOR | 1.00 | LS |
0.92
| 0.91 | 0.01 | $230,000.00 | $2,300.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.44
| 0.37 | 0.07 | $454,000.00 | $31,780.00 |
| S-05 | MODIFY SPILLWAY OPENINGS | | LS |
1.00
| 0.00 | 1.00 | $22,500.00 | $22,500.00 |
| S-06 | REMOVABLE LOUVER & ADDED REBAR AT CONTROL BLDG. | | LS |
0.50
| 0.00 | 0.50 | $20,200.00 | $10,100.00 |
| S-07 | INTAKE TOWER MODIFIED CONNECTION | | LS |
0.50
| 0.00 | 0.50 | $48,000.00 | $24,000.00 |
|