| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $35,000.00 | $7,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $35,000.00 | $7,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $35,000.00 | $7,000.00 |
| 8 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
0.50
| 0.00 | 0.50 | $18,200.00 | $9,100.00 |
| 10 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $20,000.00 | $4,000.00 |
| 12 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 13 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $300,000.00 | $60,000.00 |
| 14 | DEMOLITION | 1.00 | LS |
0.80
| 0.50 | 0.30 | $150,000.00 | $45,000.00 |
| 36 | CLEARING AND GRUBBING | 1.00 | LS |
0.025
| 0.00 | 0.025 | $200,000.00 | $5,000.00 |
| 38 | AGRONOMIC SOIL REPORT | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 40 | TRAFFIC CONTROL | 1.00 | LS |
0.40
| 0.20 | 0.20 | $35,000.00 | $7,000.00 |
| 43 | 4-INCH PVC SCHEDULE 80 CONDUIT FOR CORDOVA WALK PUMP STATION | 85.00 | LF |
14.00
| 0.00 | 14.00 | $200.00 | $2,800.00 |
| 44 | MANUAL TRANSFER SWITCH | 2.00 | EA |
0.10
| 0.00 | 0.10 | $50,000.00 | $5,000.00 |
| 46 | METERED MAIN SERVICE PANEL AND CONDUIT/WIRE | 1.00 | LS |
0.24
| 0.00 | 0.24 | $50,000.00 | $12,000.00 |
| 47 | DISTRIBUTION PANEL AND WIRE/CONDUIT | 2.00 | EA |
0.238
| 0.00 | 0.238 | $100,000.00 | $23,800.00 |
| 53 | BUBBLER PANEL AND WIRE/CONDUIT | 2.00 | EA |
0.5184
| 0.00 | 0.5184 | $25,000.00 | $12,960.00 |
| 59 | LIGHTING AND WIRE/CONDUIT FOR CORDOVA WALK PUMP STATION | 1.00 | LS |
0.559
| 0.00 | 0.559 | $50,000.00 | $27,950.00 |
| 60 | LIGHTING AND WIRE/CONDUIT FOR NAPLES PUMP STATION | 1.00 | LS |
0.559
| 0.00 | 0.559 | $50,000.00 | $27,950.00 |
| 68 | PORTABLE GENERATOR RENTAL FOR CORDOVA WALK PUMP STATION | 6.00 | MO |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 76 | SHORING OF OPEN EXCAVATIONS FOR CORDOVA WALK PUMP STATION | 1.00 | LS |
0.40
| 0.00 | 0.40 | $120,000.00 | $48,000.00 |
| 77 | SHORING OF OPEN EXCAVATIONS FOR NAPLES PUMP STATION | 1.00 | LS |
0.65
| 0.00 | 0.65 | $150,000.00 | $97,500.00 |
| 79 | 4-INCH PVC SCHEDULE 80 CONDUIT FOR NAPLES PUMP STATION | 160.00 | LF |
151.00
| 0.00 | 151.00 | $200.00 | $30,200.00 |
|