Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Chatsworth - Lake Manor Drive et al
Contractor: All American Asphalt
P.O. Box 2229
Corona, CA 92878-2229
Project ID: RMD3508001
Federal Number(s): None
Original Contract: $2,445,363.52
Awarded: 12/8/2025
Period Ending: 7/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.15 0.000.15$3,300.00$495.00
5IMPLEMENTATION OF BMPS1.00LS 0.15 0.000.15$13,000.00$1,950.00
9MOBILIZATION1.00LS 0.445 0.000.445$275,000.00$122,375.00
10TRAFFIC CONTROL1.00LS 0.15 0.000.15$360,000.00$54,000.00
11CLEARING AND GRUBBING1.00LS 1.00 0.001.00$30,000.00$30,000.00
12CONCRETE REMOVAL (NON-REINFORCED)49.00CY 25.16 0.0025.16$850.00$21,386.00
13UNCLASSIFIED EXCAVATION985.00CY 81.08 0.0081.08$205.00$16,621.40
14CRUSHED MISCELLANEOUS BASE309.00CY 22.74 0.0022.74$200.00$4,548.00
27PCC PAVEMENT15.00CY 3.85 0.003.85$1,250.00$4,812.50
28PCC CURB, TYPE A1-660.00LF 23.00 0.0023.00$70.00$1,610.00
29PCC CURB, TYPE A1-6 (MOD)18.00LF 4.00 0.004.00$75.00$300.00
31PCC CURB, TYPE A1-VAR111.00LF 41.00 0.0041.00$85.00$3,485.00
33PCC CURB & GUTTER, TYPE A2-656.00LF 56.00 0.0056.00$105.00$5,880.00
35PCC CURB & GUTTER, TYPE A2-VAR27.00LF 27.00 0.0027.00$135.00$3,645.00
491" CONDUIT (SCH 80 PVC)43.00LF 43.00 0.0043.00$55.00$2,365.00
502" CONDUIT (SCH 80 PVC)15.00LF 15.00 0.0015.00$190.00$2,850.00
513" CONDUIT (SCH 80 PVC)142.00LF 27.00 0.0027.00$125.00$3,375.00
7512-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)465.00LF 160.00 0.00160.00$7.00$1,120.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $283,317.90 $0.00 $283,317.90
Retained $14,165.90 $0.00 $14,165.90
Deducted $0.00 $0.00 $0.00
Due $269,152.00 $0.00 $269,152.00