Progress Payment 6
Project Name: Marie Canyon Stormwater Disinfection System Upgrade
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001374
Federal Number(s): None
Original Contract: $1,646,300.00
Awarded: 4/15/2025
Period Ending: 8/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF BMPS1.00LS 0.95 0.800.15$22,137.00$3,320.55
6IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 1.00 0.800.20$7,379.00$1,475.80
10TRAFFIC CONTROL1.00LS 0.90 0.800.10$29,517.00$2,951.70
11IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.800.20$11,069.00$2,213.80
14MISCELLANEOUS MECHANICAL WORK1.00LS 1.00 0.520.48$66,707.00$32,019.36
15ELECTRICAL WORK1.00LS 1.00 0.550.45$472,583.00$212,662.35
17ULTRAVIOLET DISINFECTION SYSTEM1.00LS 1.00 0.001.00$76,058.00$76,058.00
18REMOVAL AND RECYCLING OF UNIVERSAL WASTE1.00LS 0.95 0.900.05$6,641.00$332.05
19SELF-PRIMING PUMP1.00LS 1.00 0.001.00$35,184.00$35,184.00
21SCREEN FILTERS1.00LS 1.00 0.900.10$76,448.00$7,644.80
24IMPLEMENTATION OF TEMPORARY BYPASS1.00LS 1.00 0.900.10$27,095.00$2,709.50
S-2ADDED INFLUENT FLOW METER LS 1.00 0.001.00$24,900.12$24,900.12
S-3GAC FILTRATION SYSTEM LS 1.00 0.800.20$701,614.00$140,322.80
S-4FOOT VALVE LS 1.00 0.001.00$2,391.88$2,391.88
S-8HANDRAIL MODIFICATION LS 1.00 0.001.00$3,500.00$3,500.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 19.00 0.0019.00$2,000.00 $38,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,748,750.22 $1,201,063.51 $547,686.71
Retained $27,384.33 $0.00 $27,384.33
Deducted $40,000.00 $2,000.00 $38,000.00
Due $1,681,365.89 $1,199,063.51 $482,302.38