| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.80
| 0.50 | 0.30 | $24,310.22 | $7,293.07 |
| 6 | IMPLEMENTAION OF THE SURFACE WATER DIVERSION PLAN | 1.00 | LS |
0.90
| 0.78 | 0.12 | $22,602.25 | $2,712.27 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.50 | 0.50 | $55,600.00 | $27,800.00 |
| 10 | RELOCATE EXISTING CHAIN LINK FENCE | 65.00 | LF |
65.00
| 60.00 | 5.00 | $95.00 | $475.00 |
| 12 | STRUCTURE BACKFILL | 65.00 | CY |
65.00
| 0.00 | 65.00 | $690.25 | $44,866.25 |
| 13 | STRUCTURE CONCRETE | 50.00 | CY |
50.00
| 40.50 | 9.50 | $2,900.45 | $27,554.28 |
| 17 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.50 | 0.40 | $25,988.10 | $10,395.24 |
| S-1 | BAR REINFORCING STEEL QTY INCREASE | | LB |
2,618.00
| 0.00 | 2,618.00 | $9.05 | $23,692.90 |
| S-2 | STRUCTURAL STEEL QUANTITY INCREASE | | LB |
284.00
| 0.00 | 284.00 | $22.50 | $6,390.00 |