Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: BI 0107 Channel Invert Repair and East Canyon Channel Wall Replacement
Contractor: PK Construction
1227 Jacaranda place
Upland, CA 91784
Project ID: FCC0001401
Federal Number(s): None
Original Contract: $594,105.02
Awarded: 2/26/2026
Period Ending: 8/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)4.00MTH 2.00 1.001.00$500.00$500.00
4IMPLEMENTATION OF BMPS1.00LS 0.80 0.500.30$24,310.22$7,293.07
6IMPLEMENTAION OF THE SURFACE WATER DIVERSION PLAN1.00LS 0.90 0.780.12$22,602.25$2,712.27
7SHORING OF OPEN EXCAVATIONS1.00LS 1.00 0.500.50$55,600.00$27,800.00
10RELOCATE EXISTING CHAIN LINK FENCE65.00LF 65.00 60.005.00$95.00$475.00
12STRUCTURE BACKFILL65.00CY 65.00 0.0065.00$690.25$44,866.25
13STRUCTURE CONCRETE50.00CY 50.00 40.509.50$2,900.45$27,554.28
17TRAFFIC CONTROL1.00LS 0.90 0.500.40$25,988.10$10,395.24
S-1BAR REINFORCING STEEL QTY INCREASE LB 2,618.00 0.002,618.00$9.05$23,692.90
S-2STRUCTURAL STEEL QUANTITY INCREASE LB 284.00 0.00284.00$22.50$6,390.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $601,177.56 $449,498.55 $151,679.01
Retained $30,058.88 $22,474.93 $7,583.95
Deducted $0.00 $0.00 $0.00
Due $571,118.68 $427,023.62 $144,095.06



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.