Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Dominguez Pump Station Rehabilitation
Contractor: Innovative Construction Solutions
575 Anton Blvd. Suite 850
Costa Mesa, CA 92626
Project ID: FCC0001393
Federal Number(s): None
Original Contract: $7,669,929.00
Awarded: 4/10/2025
Period Ending: 8/6/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 3.00 2.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.50 0.400.10$15,000.00$1,500.00
5IMPLEMENTATION OF BMPS1.00LS 0.50 0.400.10$5,000.00$500.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.50 0.400.10$20,000.00$2,000.00
14OFFICE FACILITIES6.00MTH 2.80 1.801.00$11,000.00$11,000.00
15MOBILIZATION1.00LS 0.75 0.500.25$140,000.00$35,000.00
16DEMOLITION1.00LS 0.60 0.500.10$150,000.00$15,000.00
18TRASH RACK1.00LS 0.70 0.000.70$225,000.00$157,500.00
19MISCELLANEOUS MECHANICAL WORKS1.00LS 0.35 0.300.05$140,000.00$7,000.00
2136 INCHES VERTICAL AXIAL FLOW PROPELLER PUMP WITH EXISTING RIGHT ANGLE GEAR DRIVE2.00EA 0.20 0.000.20$420,000.00$84,000.00
22ELECTRICAL WORK1.00LS 0.15 0.080.07$1,425,000.00$99,750.00
27FIBERGLASS REINFORCED POLYMER GRATING1,002.00SF 100.00 0.00100.00$50.00$5,000.00
28FIBERGLASS REINFORCED POLYMER HANDRAIL296.00LF 30.00 0.0030.00$150.00$4,500.00
35TRAFFIC CONTROL1.00LS 0.65 0.600.05$5,000.00$250.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGETED WORKER HIRING PROGRAMVIOLATION 654.48 0.00654.48$1.00 $654.48

FINANCIAL SUMMARY

  Total Previous Current
Earned $945,210.00 $521,710.00 $423,500.00
Retained $47,260.50 $26,085.50 $21,175.00
Deducted $654.48 $0.00 $654.48
Due $897,295.02 $495,624.50 $401,670.52



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.