| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 15.00 | MTH |
12.00
| 11.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.84
| 0.76 | 0.08 | $324,000.00 | $25,920.00 |
| 8 | NOISE MONITORING AND REPORTING | 15.00 | MTH |
12.00
| 11.00 | 1.00 | $4,000.00 | $4,000.00 |
| 20 | WATER TRUCK | 260.00 | DAY |
227.50
| 204.50 | 23.00 | $1,800.00 | $41,400.00 |
| 23 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.84
| 0.76 | 0.08 | $34,000.00 | $2,720.00 |
| 27 | OFFICE FACILITIES | 15.00 | MTH |
12.00
| 11.00 | 1.00 | $5,000.00 | $5,000.00 |
| 38 | PERMEABLE ZONE MATERIAL | 2,691.00 | CY |
1,240.00
| 1,140.00 | 100.00 | $80.00 | $8,000.00 |
| 39 | BUTTRESS FILL | 16,505.00 | CY |
15,362.40
| 14,577.10 | 785.30 | $55.00 | $43,191.50 |
| 40 | DOWNSTREAM RIPRAP (CLASS IV) | 7,571.00 | CY |
5,715.08
| 4,904.94 | 810.14 | $75.00 | $60,760.50 |
| 41 | UPSTREAM RIPRAP (CLASS V) | 8,792.00 | CY |
3,436.45
| 2,790.11 | 646.34 | $50.00 | $32,317.00 |
| 43 | PCC PAVEMENT & PCC WALKWAY | 1,202.00 | CY |
278.39
| 0.00 | 278.39 | $550.00 | $153,114.50 |
| 50 | 48" RCP & APPURTENANCES | 150.00 | LF |
150.00
| 109.00 | 41.00 | $720.00 | $29,520.00 |
| 67 | 8" CLEANOUT RISER | 4.00 | EA |
4.00
| 3.00 | 1.00 | $6,100.00 | $6,100.00 |
| 72 | TOE DRAIN WEIR VAULT | 1.00 | LS |
0.09
| 0.05 | 0.04 | $22,000.00 | $880.00 |
| 74 | SPILLWAY WALL BUTTRESS COMPLETE IN PLACE | 1.00 | LS |
0.95
| 0.86 | 0.09 | $6,000,000.00 | $540,000.00 |
| 75 | INTAKE TOWER COMPLETE IN PLACE | 1.00 | LS |
0.70
| 0.56 | 0.14 | $1,500,000.00 | $210,000.00 |
| 77 | INTAKE TOWER TRASH RACK COMPLETE IN PLACE | 1.00 | LS |
0.97
| 0.90 | 0.07 | $445,000.00 | $31,150.00 |
| 78 | CATWALK & STAIRWAY COMPLETE IN PLACE | 1.00 | LS |
1.00
| 0.17 | 0.83 | $184,000.00 | $152,720.00 |
| 79 | CATWALK STRUCTURAL (STEEL, PLATE, HANDRAILING) | 1.00 | LS |
0.20
| 0.04 | 0.16 | $550,000.00 | $88,000.00 |
| 80 | CONTROL BUILDING | 1.00 | LS |
0.80
| 0.62 | 0.18 | $700,000.00 | $126,000.00 |
| 82 | ELECTRICAL WORK | 1.00 | LS |
0.65
| 0.44 | 0.21 | $454,000.00 | $95,340.00 |
| 83 | INSTRUMENTATION | 1.00 | LS |
0.65
| 0.55 | 0.10 | $425,000.00 | $42,500.00 |
| S-07 | INTAKE TOWER MODIFIED CONNECTION | | LS |
1.00
| 0.50 | 0.50 | $48,000.00 | $24,000.00 |
|