Los Angeles County Public Works
Project Management Division III
Progress Payment 12
Project Name: Santa Anita Debris Dam Seismic Strengthening Project
Contractor: AMES CONSTRUCTION INC
2500 County Road 42 West
Burnsville , MN 55337
Project ID: FCC0001272
Federal Number(s): None
Original Contract: $20,467,899.50
Awarded: 6/11/2025
Period Ending: 8/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)15.00MTH 12.00 11.001.00$500.00$500.00
5IMPLEMENTATION OF THE SWPPP1.00LS 0.84 0.760.08$324,000.00$25,920.00
8NOISE MONITORING AND REPORTING15.00MTH 12.00 11.001.00$4,000.00$4,000.00
20WATER TRUCK260.00DAY 227.50 204.5023.00$1,800.00$41,400.00
23IMPLEMENTATION OF THE LTWHP1.00LS 0.84 0.760.08$34,000.00$2,720.00
27OFFICE FACILITIES15.00MTH 12.00 11.001.00$5,000.00$5,000.00
38PERMEABLE ZONE MATERIAL2,691.00CY 1,240.00 1,140.00100.00$80.00$8,000.00
39BUTTRESS FILL16,505.00CY 15,362.40 14,577.10785.30$55.00$43,191.50
40DOWNSTREAM RIPRAP (CLASS IV)7,571.00CY 5,715.08 4,904.94810.14$75.00$60,760.50
41UPSTREAM RIPRAP (CLASS V)8,792.00CY 3,436.45 2,790.11646.34$50.00$32,317.00
43PCC PAVEMENT & PCC WALKWAY1,202.00CY 278.39 0.00278.39$550.00$153,114.50
5048" RCP & APPURTENANCES150.00LF 150.00 109.0041.00$720.00$29,520.00
678" CLEANOUT RISER4.00EA 4.00 3.001.00$6,100.00$6,100.00
72TOE DRAIN WEIR VAULT1.00LS 0.09 0.050.04$22,000.00$880.00
74SPILLWAY WALL BUTTRESS COMPLETE IN PLACE1.00LS 0.95 0.860.09$6,000,000.00$540,000.00
75INTAKE TOWER COMPLETE IN PLACE1.00LS 0.70 0.560.14$1,500,000.00$210,000.00
77INTAKE TOWER TRASH RACK COMPLETE IN PLACE1.00LS 0.97 0.900.07$445,000.00$31,150.00
78CATWALK & STAIRWAY COMPLETE IN PLACE1.00LS 1.00 0.170.83$184,000.00$152,720.00
79CATWALK STRUCTURAL (STEEL, PLATE, HANDRAILING)1.00LS 0.20 0.040.16$550,000.00$88,000.00
80CONTROL BUILDING1.00LS 0.80 0.620.18$700,000.00$126,000.00
82ELECTRICAL WORK1.00LS 0.65 0.440.21$454,000.00$95,340.00
83INSTRUMENTATION1.00LS 0.65 0.550.10$425,000.00$42,500.00
S-07INTAKE TOWER MODIFIED CONNECTION LS 1.00 0.500.50$48,000.00$24,000.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 0.00 271.84-271.84$1.00 ($271.84)

FINANCIAL SUMMARY

  Total Previous Current
Earned $16,677,103.97 $14,953,970.47 $1,723,133.50
Retained $833,855.20 $747,698.52 $86,156.68
Deducted $0.00 $271.84 ($271.84)
Due $15,843,248.77 $14,206,000.11 $1,637,248.66



Contact Office Engineer
Contractor Copy  