Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: South Street TSSP - Atlantic Avenue to Studebaker Road
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TSM0010286
Federal Number(s): None
Original Contract: $687,441.00
Awarded: 7/15/2025
Period Ending: 8/20/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)7.00MTH 6.00 5.001.00$500.00$500.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
14#6 WIRE40.00LF 40.00 0.0040.00$3.20$128.00
16#12 WIRE150.00LF 150.00 0.00150.00$2.00$300.00
19REMOVE TYPE 332 CABINET1.00EA 1.00 0.001.00$1,000.00$1,000.00
50TYPE III-B SERVICE CABINET FOUNDATION1.00EA 1.00 0.001.00$3,200.00$3,200.00
S-8LONG BEACH LIST OF WORK - SIGNAGE (CO #8) LS 1.00 0.850.15$30,571.20$4,585.68
S-12SCE WORK ORDER MAP WORK (CO #12) LS 1.00 0.001.00$42,000.00$42,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $783,934.38 $731,220.70 $52,713.68
Retained $39,196.72 $36,561.04 $2,635.68
Deducted $0.00 $0.00 $0.00
Due $744,737.66 $694,659.66 $50,078.00