| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 2.00 | 1.00 | $1,500.00 | $1,500.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.00 | 1.00 | $13,754.00 | $13,754.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.25 | 0.75 | $4,000.00 | $3,000.00 |
| 6 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.25 | 0.75 | $57,807.00 | $43,355.25 |
| 7 | PROPOSED LAYOUT OVERLAYED ON SITE SURVEY | 40.00 | EA |
40.00
| 19.00 | 21.00 | $392.00 | $8,232.00 |
| 8 | CONCRETE REMOVAL WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
74.76
| 46.76 | 28.00 | $1,661.00 | $46,508.00 |
| 9 | CONCRETE REMOVAL OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
82.95
| 58.41 | 24.54 | $600.00 | $14,724.00 |
| 10 | CONCRETE REPLACEMENT WITHIN BUS SHELTER FOOTPRINT | 200.00 | CY |
107.66
| 65.46 | 42.20 | $1,837.00 | $77,521.40 |
| 11 | CONCRETE REPLACEMENT OUTSIDE BUS SHELTER FOOTPRINT | 89.00 | CY |
84.32
| 59.78 | 24.54 | $600.00 | $14,724.00 |
| 12 | SOLAR POWERED BUS SHELTER WITH AD KIOSKS | 25.00 | EA |
25.00
| 23.00 | 2.00 | $22,000.00 | $44,000.00 |
| 13 | LABOR AND INSTALLATION OF SOLAR POWERED BUS SHELTER | 25.00 | EA |
25.00
| 0.00 | 25.00 | $5,011.00 | $125,275.00 |
| 15 | LABOR AND INSTALLATION OF HARD WIRED BUS SHELTER | 15.00 | EA |
15.00
| 0.00 | 15.00 | $5,460.00 | $81,900.00 |
| 16 | FURNISH AND INSTALL BUS BENCH | 40.00 | EA |
40.00
| 30.00 | 10.00 | $1,103.00 | $11,030.00 |
| 17 | FURNISH AND INSTALL TRASH RECEPTACLE | 40.00 | EA |
40.00
| 30.00 | 10.00 | $1,233.00 | $12,330.00 |
| 18 | FURNISH AND INSTALL BICYCLE RACK | 40.00 | EA |
40.00
| 30.00 | 10.00 | $457.00 | $4,570.00 |
| S-1 | MATERIAL PROCUREMENT DELAY NTP 1 EXTENSION (CO #1) | | DAY |
100.00
| 0.00 | 100.00 | $0.00 | $0.00 |
| S-2 | TIME EXTENSION DUE TO MATERIAL PROCUREMENT DELAY TO TARIFF | | DAYS |
74.00
| 0.00 | 74.00 | $0.00 | $0.00 |
| S-11 | RE-ROUTE CHAIN-LINK FENCE AT LOC. NO. 24 (CO #11) | | LS |
1.00
| 0.00 | 1.00 | $9,817.73 | $9,817.73 |
| S-12 | REPAIR EXISTING UPLIFTED SIDEWALK SECTION LOCATION 34 | | LS |
1.00
| 0.00 | 1.00 | $2,400.00 | $2,400.00 |
| S-13 | R&R EXISTING CURB DRAIN AT LOC. 38 | | LS |
1.00
| 0.00 | 1.00 | $4,721.09 | $4,721.09 |