| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.00 | 0.40 | $25,698.00 | $10,279.20 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.25 | 0.15 | $9,676.00 | $1,451.40 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.25 | 0.15 | $8,567.00 | $1,285.05 |
| 8 | OFFICE FACILITIES | 6.00 | MTH |
1.50
| 0.50 | 1.00 | $5,480.67 | $5,480.67 |
| 9 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $73,653.00 | $14,730.60 |
| 11 | DEMOLITION | 1.00 | LS |
0.90
| 0.50 | 0.40 | $24,261.00 | $9,704.40 |
| 13 | FENCES | 1.00 | LS |
0.50
| 0.10 | 0.40 | $270,406.00 | $108,162.40 |
| 14 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
0.60
| 0.10 | 0.50 | $67,397.00 | $33,698.50 |
| 18 | ELECTRICAL WORK | 1.00 | LS |
0.45
| 0.30 | 0.15 | $607,095.00 | $91,064.25 |
| S-2 | NTP 1 EXTENSION | | NWD |
16.00
| 0.00 | 16.00 | $0.00 | $0.00 |