| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.45
| 0.30 | 0.15 | $3,300.00 | $495.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.45
| 0.30 | 0.15 | $13,000.00 | $1,950.00 |
| 6 | PREPARATION OF THE TWW WORKPLAN (STIPULATED PRICE OF $2500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 8 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 1.00 | 1.00 | $3,500.00 | $3,500.00 |
| 9 | MOBILIZATION | 1.00 | LS |
0.8448
| 0.667 | 0.1778 | $275,000.00 | $48,895.00 |
| 10 | TRAFFIC CONTROL | 1.00 | LS |
0.45
| 0.30 | 0.15 | $360,000.00 | $54,000.00 |
| 13 | UNCLASSIFIED EXCAVATION | 985.00 | CY |
202.21
| 106.83 | 95.38 | $205.00 | $19,552.90 |
| 14 | CRUSHED MISCELLANEOUS BASE | 309.00 | CY |
131.32
| 55.01 | 76.31 | $200.00 | $15,262.00 |
| 17 | AC CURB, TYPE D1-6 | 270.00 | LF |
270.00
| 0.00 | 270.00 | $35.00 | $9,450.00 |
| 18 | AC CURB, TYPE D1-VAR | 18.00 | LF |
18.00
| 0.00 | 18.00 | $45.00 | $810.00 |
| 19 | AC PAVEMENT | 1,266.00 | TON |
6.14
| 0.00 | 6.14 | $155.00 | $951.70 |
| 20 | AC PAVEMENT (SIDEWALK) | 49.00 | TON |
48.14
| 0.00 | 48.14 | $560.00 | $26,958.40 |
| 21 | AC PAVEMENT(PATCH BACK) | 57.00 | TON |
53.95
| 25.71 | 28.24 | $560.00 | $15,814.40 |
| 29 | PCC CURB, TYPE A1-6 (MOD) | 18.00 | LF |
10.00
| 4.00 | 6.00 | $75.00 | $450.00 |
| 32 | PCC CURB, TYPE A1-VAR (MOD) | 12.00 | LF |
12.00
| 10.00 | 2.00 | $105.00 | $210.00 |
| 37 | PCC WALK, 4" THICK | 2,316.00 | SF |
2,051.80
| 1,597.25 | 454.55 | $22.00 | $10,000.10 |
| 38 | PCC CURB RAMPS | 6.00 | CY |
4.38
| 0.00 | 4.38 | $1,700.00 | $7,446.00 |
| 40 | DETECTABLE WARNING SURFACE | 105.00 | SF |
105.00
| 0.00 | 105.00 | $105.00 | $11,025.00 |