Progress Payment 15
Project Name: Boone Olive Pump Station Upgrade Project
Contractor: Metro Builders & Engineers Group, LTD
2610 Avon Street
Newport Beach, CA 92663
Project ID: FCC0001386
Federal Number(s): None
Original Contract: $4,723,065.00
Awarded: 4/10/2024
Period Ending: 8/18/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
20ELECTRICAL1.00LS 1.00 0.950.05$487,566.00$24,378.30
27VALVES, PIPES AND FITTINGS1.00LS 1.00 0.900.10$67,550.00$6,755.00
S-16AWELD CAP & BACKFILL ABANDONED 14" PIPE LS 9,000.00 0.009,000.00$1.00$9,000.00
S-18ADDITIONAL SUMP PUMP PIPE SUPPORT  LS 1.00 0.001.00$2,900.00$2,900.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 49.00 7.0042.00$2,000.00 $84,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,892,665.02 $4,849,631.72 $43,033.30
Retained $244,633.25 $242,481.59 $2,151.66
Deducted $98,362.10 $14,362.10 $84,000.00
Due $4,549,669.67 $4,592,788.03 ($43,118.36)



During the initial processing of this Engineer's Monthly Estimate, the current earnings were found to be less than the combined total of the current retention and current deductions resulting in a "negative payment" condition. In order to resolve the condition, the total retention amount for this project has automatically been decreased