| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.50 | 0.10 | $15,000.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.50 | 0.10 | $5,000.00 | $500.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.60
| 0.50 | 0.10 | $20,000.00 | $2,000.00 |
| 14 | OFFICE FACILITIES | 6.00 | MTH |
3.80
| 2.80 | 1.00 | $11,000.00 | $11,000.00 |
| 15 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $140,000.00 | $28,000.00 |
| 16 | DEMOLITION | 1.00 | LS |
0.70
| 0.60 | 0.10 | $150,000.00 | $15,000.00 |
| 18 | TRASH RACK | 1.00 | LS |
0.98
| 0.70 | 0.28 | $225,000.00 | $63,000.00 |
| 19 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
0.45
| 0.35 | 0.10 | $140,000.00 | $14,000.00 |
| 20 | 48 INCHES VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR | 3.00 | EA |
0.20
| 0.00 | 0.20 | $830,000.00 | $166,000.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
0.30
| 0.15 | 0.15 | $1,425,000.00 | $213,750.00 |
| 25 | STRUCTURAL STEEL | 28,317.00 | LB |
10,000.00
| 0.00 | 10,000.00 | $23.00 | $230,000.00 |
| 26 | STAIR TREADS | 1.00 | LS |
0.10
| 0.00 | 0.10 | $35,000.00 | $3,500.00 |
| 29 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 159.00 | LF |
34.00
| 0.00 | 34.00 | $50.00 | $1,700.00 |
| 32 | BAR REINFORCING STEEL | 474.00 | LB |
100.00
| 0.00 | 100.00 | $12.00 | $1,200.00 |
| 34 | DAVIT SLEEVE | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,500.00 | $3,500.00 |
| 35 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.65 | 0.05 | $5,000.00 | $250.00 |
|