Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Main Street-Las Tunas Drive TSSP - Huntington Drive to Golden West Avenue
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010248
Federal Number(s): None
Original Contract: $1,338,580.70
Awarded: 11/25/2025
Period Ending: 9/18/2026
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.20 0.000.20$2,000.00$400.00
5IMPLEMENTATION OF BMPS1.00LS 0.20 0.000.20$2,500.00$500.00
6MOBILIZATION1.00LS 0.75 0.000.75$47,897.00$35,922.75
7EXPLORATORY EXCAVATION OF UTILITIES (ALLOWANCE OF $18,750)18,750.00AL 2,400.00 0.002,400.00$1.00$2,400.00
172" CONDUIT (SCH 80 PVC)40.00LF 2.00 0.002.00$100.00$200.00
183" CONDUIT (SCH 80 PVC)805.00LF 671.00 0.00671.00$85.00$57,035.00
194" CONDUIT (SCH 80 PVC)80.00LF 80.00 0.0080.00$100.00$8,000.00
96TRAFFIC CONTROL1.00LS 0.20 0.000.20$28,000.00$5,600.00
97FLASHING ARROW SIGN2.00EA 2.00 0.002.00$1,000.00$2,000.00
98CHANGEABLE MESSAGE SIGN2.00EA 2.00 0.002.00$2,400.00$4,800.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $119,857.75 $0.00 $119,857.75
Retained $5,992.89 $0.00 $5,992.89
Deducted $0.00 $0.00 $0.00
Due $113,864.86 $0.00 $113,864.86



Contact Office Engineer
Contractor Copy  